(7,500 cars) x (1.25 hours/car) = 9,375 hours

(9,375 hours) / (40 hours/worker) = 234.375 workers, which, where it involves people, rounds to 235 .

Even if you stagger the shifts to have some people start on Wednesday and

work the weekend, it makes no difference. Each worker works 40 hours and

that's it, so it still takes 235 of them, regardless of which days they work.

User Avatar

Wiki User

13y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: If a man orders 7500 new cars to be delivered in one week and each car must be worked on requiring 1 hour an 15min How many workers would it take if they only work 8 hours per day for 5 days?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Where did garment workers toil?

Garment workers worked in factories.


Which organization worked for the rights of migrant farm workers?

The National Farm Workers Association worked for the rights of migrant farm workers. The organization became the United Farm Workers of America in 1962.


What three orders did Constantine issue in hopes of aiding the Roman economy?

The sons of workers had to follow there fathers traids, the sons of farmers had to work the land there fathers worked and the sons of soldiers had to serve in the army.


What did seafood workers do at work?

They worked at factories.


What do victorian field workers do?

Worked in fields


Were immigrants skilled workers when they worked in the us?

Mabye


Farm workers who were tied to the land they worked?

Serf


Places in which modern workers worked instead of at home?

they worked way way way up in der


Who worked with the organization for farm workers' rights?

Cesar Chavez


How many people worked on the Berlin Wall?

about 60,000 workers


Who worked in the twin towers BE SPECIFIC?

dead office workers


How many workers worked on oil back in the 1800s?

you face