In Critical Path Analysis using precedence diagrams (showing
activities linked by logical connections/constraints e.g. Activity
A must happen before Activity B), then the Earliest Start (Earliest
Event Time?) is the earliest time that that activity can start
according to the logical constraints of the precedence diagram and
the constraint types (Finish to Start, Start to Start, Finish to
Finish or Start to Finish).