Aerospace Supplier (Pre-Opening Schedule Ofevents)
Pre-Opening Schedule Ofevents
- November-December
- Review Articles of Incorporation and Corporate By-laws.
- Complete preliminary business plan.
- Select and engage outside professional assistance, CPA, attorney, architect and builder.
- Begin search for suitable site.
- January
- Execute legal agreement with architect.
- Begin search for financing sources.
- Continue search for site.
- February
- Finalize plans for the facility.
- Begin preliminary negotiations with the builder.
- May-June
- Reach agreement with property owner and purchase the site.
- Complete financing plans and prepare loan request.
- Complete negotiations with contractor.
- Initiate discussions with equipment suppliers and manufacturers.
- Begin negotiations to upgrade employee insurance plans.
- July
- Obtain site approval from city and county.
- Complete detailed business plan and construction plan.
- Submit financing package to lending group.
- August
- Obtain final financing approval.
- Complete site purchase.
- Begin construction.