The purpose of PERT Analysis is to identify an estimate for an activity.
This method addresses the issue of uncertainty in estimating the activity duration. The uncertainty in the duration estimate can be calculated by making a three-point estimate in which each point corresponds to one of the following estimate types:
• Most likely scenario - The activity duration is calculated in most practical terms by factoring in resources likely to be assigned, realistic expectations of the resources, dependencies, and interruptions.
• Optimistic scenario - This is the best-case version of the situation described in the most likely scenario.
• Pessimistic scenario - This is the worst-case version of the situation described in the most likely scenario.
The spread of these three estimates determines the uncertainty. The resultant duration is calculated by taking the average of the three estimates. For example, if the duration for an activity is estimated to be 20 days for the most likely scenario, 15 days for the optimistic scenario, and 25 days for the pessimistic scenario, then the average duration is 20 days, and the uncertainty is ± 5 days, which can be expressed as:
Duration = 20 ± 5 days
It's equivalent to saying that the activity duration is 20 days, give or take five days.
However, the most likely scenario may be given more weight than the other two scenarios. Therefore, the expected duration can be calculated by using the following formula:
ED = ((N*MD) + OD + PD)/(N+2)
Here
ED = Expected Duration
MD = Most likely Duration
OD = Optimistic Duration
PD = Pessimistic Duration
N = Weightage for the Most likely Duration
An approach to decision-making that identifies as few options as possible that will produce the maximum result is called pareto analysis. There are six steps that are involved when conducting a pareto analysis.
Critical Path Method (CPM) - A schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram.
PERT stands for Program Evaluation and Review Technique. It is a project management methodology used to analyze and manage tasks involved in completing a project. PERT helps in determining the duration of the entire project by estimating the time required for each task and identifying the critical path.
35.56 cmAlgebraic Steps / Dimensional Analysis Formula14in*2.54 cm1 in=35.56cm
113 inches = 287.02 centimeters.Algebraic Steps / Dimensional Analysis Formula113 in*2.54 cm 1 in=287.02 cm
various method or steps involved in gravimeteic analysis are as followsprecipitationfiltrationwashingdrying or ignitionweighing
Both are used for planning and scheduling. Steps to create both networks are similar
Dana C. Rooks has written: 'PERT' -- subject(s): Bibliography, PERT (Network analysis)
Joseph J. Moder has written: 'Project management with CPM, PERT, and precedence diagramming' -- subject(s): Critical path analysis, PERT (Network analysis), Project management
Can't post images here to give you a decent example of the PERT chart, here's an article on the subject: http://www.pmhut.com/using-pert-analysis , the article also explains how to make a PERT chart in MS Project.
H. E. R. Colyer has written: 'PERT and CPM bibliography' -- subject(s): Bibliography, Construction industry, Management, Critical path analysis, PERT (Network analysis)
An approach to decision-making that identifies as few options as possible that will produce the maximum result is called pareto analysis. There are six steps that are involved when conducting a pareto analysis.
There are a number of steps involved in decision making process. Some of the key steps include gathering relevant information, analysis and evaluation of the information gathered and comparing the various options available before making a decision.
What are the steps in conducting job analysis
M. Krishnamoorthy has written: 'Critical path method' -- subject(s): PERT (Network analysis), Critical path analysis
Statistical Control Reports Break Even Analysis PERT CPM
Anthony L. Iannone has written: 'Management program planning and control with PERT, MOST and LOB' -- subject(s): Line of balance (Management), PERT (Network analysis)