
Big Dig is the unofficial name of the Central Artery/Tunnel Project (CA/T), a
The final ramp opened
The Big Dig has been the most expensive highway project in the U.S.[1] Although the project was estimated at $2.8 billion in 1985 (in
1982 dollars), over $14.6 billion had been spent in federal and state tax dollars as of 2006.
[2] The project has incurred criminal arrests,
Historical background
Boston's historically tangled streets were laid out long before the advent of the
Built before strict federal Interstate Highway standards were developed
during the Eisenhower administration, the expressway was plagued by tight turns, an
excessive number of entrances and exits, entrance ramps without merge lanes, and continually escalating vehicular loads. Local
businesses again wanted relief, historians sought a reuniting of the waterfront with the city, and nearby residents desired
removal of this "Green Monster". (Its matte green paint prompted
Early planning
The project was conceived in the 1970s by the
Planning for the Big Dig as a project officially began in 1982, with environmental impact studies starting in 1983. After
years of extensive lobbying for federal dollars, a 1987 public works bill appropriating funding for the Big Dig was passed by
Obstacles
In addition to these political and financial difficulties, the project faced several environmental and engineering obstacles.
The downtown area through which the tunnels were to be dug was largely landfill, and included existing subway lines as well as innumerable pipes and utility lines that would have to be replaced or moved. Tunnel workers encountered many unexpected geological and archaeological barriers, ranging from glacial debris to foundations of buried houses and a number of sunken ships lying within the reclaimed land.
The project received approval from state environmental agencies in 1991, after satisfying concerns including release of toxins
by the excavation and the possibility of disrupting the homes of millions of
Reworking such a busy corridor without seriously restricting traffic flow required a number of state-of-the-art construction techniques. Because the old elevated highway (which remained in operation throughout the construction process) rested on pylons located throughout the designated dig area, engineers first utilized slurry wall techniques to create 120 ft.-deep concrete walls upon which the highway could rest. These concrete walls also stabilized the sides of the site, preventing cave-ins during the excavation process.
The multilane interstates also had to pass under South Station's 7 tracks which carried over 40,000 commuters and 400 trains
per day. In order to avoid multiple relocations of the train lines while the tunnelling
advanced, as had been initially planned, a specially designed
Other challenges included an existing subway tunnel crossing the path of the underground highway. In order to build
Construction phase
The Central Artery/Tunnel Project was managed by the Massachusetts Turnpike Authority with design and construction supervised
by a joint venture of
The nature of the Charles River crossing had been a source of major controversy throughout the design phase of the project.
Many environmental advocates preferred a river crossing entirely in tunnels, but this, along with 27 other plans, was rejected as
too costly. Finally, with a deadline looming to begin construction on a separate project that would connect the Tobin Bridge to the Charles River crossing, Salvucci overrode the objections and chose a variant of the
plan known as "Scheme Z". This plan was considered to be reasonably cost-effective, but had the drawback of requiring highway
ramps stacked up as high as 100 feet (30 m) immediately adjacent to the Charles River. The city of
Boston blue
The Zakim Bunker Hill Bridge, designed by Swiss designer Christian Menn, is the terminus of the project, connecting the underground highway with I-93 and US 1. The distinctive cable-stayed bridge is supported by two forked towers connected to the span by cables and girders.
The
When construction began, the project cost, including the Charles River crossing, was estimated at $5.8 billion. Eventual cost
overruns were so high that the chairman of the Massachusetts Turnpike Authority,
Final phases
On
The next phase, moving the elevated Interstate 93 underground, was completed in two stages: northbound lanes opened in March
2003 and southbound lanes (in a temporary configuration) on December 20,
By the end of December 2004, 95% of the Big Dig was completed. Major construction remained on the surface, including
construction of final ramp configurations in the North End and in the
The final ramp downtown—exit 20B from I-93 south to Albany
Street—opened
In 2006, the two Interstate 93 tunnels were dedicated as the
Problems
"Thousands of leaks"
As far back as 2001, Turnpike Authority officials and private contractors knew of thousands of leaks in the ceiling and wall fissures, extensive water damage to steel supports and fireproofing systems, and overloaded drainage systems.[9] A $10 million contract, signed off as a cost overrun, was used to repair these leaks. Many of the leaks were a result of Modern Continental and other subcontractors failing to remove gravel and other debris before pouring concrete. This was not made publicly known to the media, but engineers at MIT (volunteer students and professors)[citation needed] did several precise experiments and found a few serious problems with the tunnel. [10]
On September 15, 2004, a major leak in the
Interstate 93 north tunnel forced the closure of the tunnel while repairs were conducted.
This also forced the Turnpike Authority to release information regarding its non-disclosure of prior leaks. A follow-up reported
on "extensive" leaks that were more severe than state authorities had previously acknowledged. The report went on to state that
the $14.6 billion tunnel system was riddled with more than 400 leaks. A
Substandard materials
On March 19, 2006, the
Fatal ceiling collapse
A fatal accident raised safety questions and closed part of the project for most of the summer of 2006. Part of the ceiling collapsed in a tunnel segment under South Boston, connecting
Following extensive inspections and repairs, Interstate 90 east and west bound lanes reopened in early January 2007.[15] The final piece of the road network, a high occupancy vehicle lane connecting Interstate 93 north to the Ted Williams Tunnel, was reopened on June 1, 2007.
On July 10,
Powers Fasteners revised their product specifications on May 15,
References
- ^ "Review Begins After Big Dig Tunnel Collapse", CNN.com, 2006-07-12. Retrieved on 2006-07-25.
- ^ Johnson, Glen. "Governor seeks to take control of Big Dig inspections", Boston Globe, 2006-07-13. Retrieved on 2006-07-13.
- ^ a b "State weighs suing 'Big Dig' contractors", International Herald Tribune, 2006-03-20. Retrieved on 2006-07-17.
- ^ Associated Press. "Boston’s ‘Big Dig’ opens to public", MSNBC, 2003-12-20. Retrieved on 2006-07-18.
- ^ Dan McNichol and Andy Ryan, The Big Dig. Silver Lining Press, 1991
- ^ Boston Central Artery Jacked Tunnels - Mott MacDonald Project Page
- ^ Leonard P. Zakim-Bunker Hill Memorial Bridge. BostonRoads.com. Retrieved on 2006-07-18.
- ^ Ross, Casey. "Hallelujah Hub drivers! Last Big Dig ramp done", Boston Herald, 2006-01-14. Retrieved on 2006-07-18.
- ^ http://www.thebostonchannel.com/bigdig/3924866/detail.html
- ^ a b "Report: Even More Big Dig Leaks Found", WCVB-TV, 2004-11-17. Retrieved on 2006-07-18.
- ^ "Romney to return contributions from Big Dig concrete workers", WPRI.
- ^ "Man dies in tunnel backup", Boston Herald, 2006-07-27. Retrieved on 2006-08-08.
- ^ "Turnpike News", Massachusetts Turnpike Authority. Retrieved on 2006-12-03.
- ^ Taurasi, Elizabeth. "Boston’s Big Dig – One of Engineering’s Biggest Mistakes?", Design News, 2006-07-28]. Retrieved on 2006-08-11. See WikiNews article here.
- ^ "Mass. tunnel ceiling inspections ordered", SeattlePi.com. Retrieved on 2006-01-07.
- ^ "Safety Board Determines Cause of Boston's Big Dig Tunnel Ceiling Collapse Last Year", ntsb.gov. Retrieved on 2006-07-12.
- ^ a b "Power-Fast®+ Epoxy Adhesive System", powers.com. Retrieved on 2007-07-12.
See also
Boston Bypass Callahan Tunnel - Conservation Law Foundation
Dublin Port Tunnel - Similar project on smaller scale in Ireland with similar problems.Interstate 90 - Interstate 93
- Leonard P. Zakim Bunker Hill Bridge
Massachusetts Turnpike - MBTA
Sumner Tunnel Ted Williams Tunnel
External links
- http://www.tsomides.com/news/downloads/Tunnel%20Design1.pdf
- Powell, Michael, "Boston's Big Dig Awash in Troubles", Washington Post, 2004-11-19, Retrieved on 2006-08-09.
- Official site
- Project map
- Boston CA/T Project History at MIT Rotch Library
- Steve Anderson's BostonRoads.com
- PBS.org – Central Artery
- Big Dig Disaster
This entry is from Wikipedia, the leading user-contributed encyclopedia. It may not have been reviewed by professional editors (see full disclaimer)





