Control chart

 
Sci-Tech Dictionary: control chart
(kən′trōl ′chärt)

(industrial engineering) A statistical tool used to detect excessive process variability due to specific assignable causes that can be corrected. It serves to determine whether a process is in a state of statistical control, that is, the extent of variation of the output of the process does not exceed that which is expected based on the natural statistical variability of the process.


Search unanswered questions...
Enter a question here...
Search: All sources Community Q&A Reference topics
Sci-Tech Encyclopedia: Control chart
Top

A graphical technique for determining whether a process is or is not in a state of statistical control. Being in statistical control means that the extent of variation of the output of the process does not exceed that which is expected on the basis of the natural statistical variability of the process. Several main types of control charts are used, based on the nature of the process and on the intended use of the data.

Every process has some inherent variability due to random factors over which there is no control and which cannot be eliminated economically. For instance, in a metal fabrication process random factors may include the distribution of impurities and structural faults among the metal molecules, vibrations of the fabrication equipment, fluctuations in the power supply that affect the speed and torque of the equipment, and variations in the operator performance from one cycle to the next. The inherent variability of the process is the aggregate result of many individual causes, each having a small impact.

The control chart technique is applicable to processes that produce a stream of discrete output units. Control charts are designed to detect excessive variability due to specific assignable causes that can be corrected. Assignable causes result in relatively large variations, and they usually can be identified and economically removed. Examples of assignable causes of variations that may occur in the example of metal fabrication include a substandard batch of raw material, a machine malfunction, and an untrained or poorly motivated operator.

A control chart is a two-dimensional plot of the evolution of the process over time. The horizontal dimension represents time, with samples displayed in chronological order, such that the earliest sample taken appears on the left and each newly acquired sample is plotted to the right. The vertical dimension represents the value of the sample statistic, which might be the sample mean, range, or standard deviation in the case of measurement by variables, or in the case of measurement by attributes, the number of nonconforming units, the fraction nonconforming, the number of nonconformities, or the average number of nonconformities per unit.

Typically a control chart includes three parallel horizontal lines (see illustration): a center line and two control limits. The center line (CL) intersects the vertical dimension at a value that represents the level of the process under stable conditions (natural variability only). The process level might be based on a given standard or, if no standard is available, on the current level of the process calculated as the average of an initial set of samples. The two lines above and below the center-line are called the upper control limit (UCL) and lower control limit (LCL) respectively, and they both denote the normal range of variation for the sample statistic. The control limits intersect the vertical axis such that if only the natural variability of the process is present, then the probability of a sample point falling outside the control limits and causing a false alarm is very small. Typically, control limits are located at three standard deviations from the center line on both sides. This results in a probability of a false alarm being equal to 0.0027.

Control chart, showing changes in average of process.
Control chart, showing changes in average of process.

The principle of operation of control charts is rather simple and consists of five general steps:

  1. Samples are drawn from the process output at regular intervals.

  2. A statistic is calculated from the observed values of the units in the sample; a statistic is a mathematical function computed on the basis of the values of the observations in the sample.

  3. The value of the statistic is charted over time; any points falling outside the control limits or any other nonrandom pattern of points indicate that there has been a change in the process, either its setting or its variability.

  4. If such change is detected, the process is stopped and an investigation is conducted to determine the causes for the change.

  5. Once the causes of the change have been ascertained and any required corrective action has been taken, the process is resumed.

The main benefit of control charts is to provide a visual means to identify conditions where the process level or variation has changed due to an assignable cause and consequently is no longer in a state of statistical control. The visual patterns that indicate either the out-of-control state or some other condition that requires attention are known as outliers, runs of points, low variability, trends, cycles, and mixtures. See also Control systems; Quality control.


Accounting Dictionary: Control Chart
Top

Graphical means of depicting sample characteristics, such as means, ranges, and attributes, over time used for process control.

Wikipedia: Control chart
Top

Control charts, also known as Shewhart charts or process-behaviour charts, in statistical process control are tools used to determine whether a manufacturing or business process is in a state of statistical control or not.

Contents

Overview

If the chart indicates that the process is currently under control then it can be used with confidence to predict the future performance of the process. If the chart indicates that the process being monitored is not in control, the pattern it reveals can help determine the source of variation to be eliminated to bring the process back into control. A control chart is a specific kind of run chart that allows significant change to be differentiated from the natural variability of the process.

This is key to effective process control and improvement. On a practical level the control chart can be seen as part of an objective disciplined approach that facilitates the decision as to whether process performance warrants attention or not.

The control chart is one of the seven basic tools of quality control (along with the histogram, Pareto chart, check sheet, cause-and-effect diagram, flowchart, and scatter diagram).

History

The control chart was invented by Walter A. Shewhart while working for Bell Labs in the 1920s. The company's engineers had been seeking to improve the reliability of their telephony transmission systems. Because amplifiers and other equipment had to be buried underground, there was a business need to reduce the frequency of failures and repairs. By 1920 they had already realized the importance of reducing variation in a manufacturing process. Moreover, they had realized that continual process-adjustment in reaction to non-conformance actually increased variation and degraded quality. Shewhart framed the problem in terms of Common- and special-causes of variation and, on May 16, 1924, wrote an internal memo introducing the control chart as a tool for distinguishing between the two. Dr. Shewhart's boss, George Edwards, recalled: "Dr. Shewhart prepared a little memorandum only about a page in length. About a third of that page was given over to a simple diagram which we would all recognize today as a schematic control chart. That diagram, and the short text which preceded and followed it, set forth all of the essential principles and considerations which are involved in what we know today as process quality control." [1] Shewhart stressed that bringing a production process into a state of statistical control, where there is only common-cause variation, and keeping it in control, is necessary to predict future output and to manage a process economically.

Dr. Shewhart created the basis for the control chart and the concept of a state of statistical control by carefully designed experiments. While Dr. Shewhart drew from pure mathematical statistical theories, he understood data from physical processes never produce a "normal distribution curve" (a Gaussian distribution, also commonly referred to as a "bell curve"). He discovered that observed variation in manufacturing data did not always behave the same way as data in nature (Brownian motion of particles). Dr. Shewhart concluded that while every process displays variation, some processes display controlled variation that is natural to the process, while others display uncontrolled variation that is not present in the process causal system at all times.[2]

In 1924 or 1925, Shewhart's innovation came to the attention of W. Edwards Deming, then working at the Hawthorne facility. Deming later worked at the United States Department of Agriculture and then became the mathematical advisor to the United States Census Bureau. Over the next half a century, Deming became the foremost champion and proponent of Shewhart's work. After the defeat of Japan at the close of World War II, Deming served as statistical consultant to the Supreme Commander of the Allied Powers. His ensuing involvement in Japanese life, and long career as an industrial consultant there, spread Shewhart's thinking, and the use of the control chart, widely in Japanese manufacturing industry throughout the 1950s and 1960s.

Chart details

A control chart consists of:

  • Points representing a statistic (e.g., a mean, range, proportion) of measurements of a quality characteristic in samples taken from the process at different times [the data]
  • The mean of this statistic using all the samples is calculated (e.g., the mean of the means, mean of the ranges, mean of the proportions)
  • A center line is drawn at the value of the mean of the statistic
  • The standard error (e.g., standard deviation/sqrt(n) for the mean) of the statistic is also calculated using all the samples
  • Upper and lower control limits (sometimes called "natural process limits") that indicate the threshold at which the process output is considered statistically 'unlikely' are drawn typically at 3 standard errors from the center line

The chart may have other optional features, including:

  • Upper and lower warning limits, drawn as separate lines, typically two standard errors above and below the center line
  • Division into zones, with the addition of rules governing frequencies of observations in each zone
  • Annotation with events of interest, as determined by the Quality Engineer in charge of the process's quality

ControlChart.svg

Chart usage

If the process is in control, all points will plot within the control limits. Any observations outside the limits, or systematic patterns within, suggest the introduction of a new (and likely unanticipated) source of variation, known as a special-cause variation. Since increased variation means increased quality costs, a control chart "signaling" the presence of a special-cause requires immediate investigation.

This makes the control limits very important decision aids. The control limits tell you about process behavior and have no intrinsic relationship to any specification targets or engineering tolerance. In practice, the process mean (and hence the center line) may not coincide with the specified value (or target) of the quality characteristic because the process' design simply can't deliver the process characteristic at the desired level.

Control charts limit specification limits or targets because of the tendency of those involved with the process (e.g., machine operators) to focus on performing to specification when in fact the least-cost course of action is to keep process variation as low as possible. Attempting to make a process whose natural center is not the same as the target perform to target specification increases process variability and increases costs significantly and is the cause of much inefficiency in operations. Process capability studies do examine the relationship between the natural process limits (the control limits) and specifications, however.

The purpose of control charts is to allow simple detection of events that are indicative of actual process change. This simple decision can be difficult where the process characteristic is continuously varying; the control chart provides statistically objective criteria of change. When change is detected and considered good its cause should be identified and possibly become the new way of working, where the change is bad then its cause should be identified and eliminated.

The purpose in adding warning limits or subdividing the control chart into zones is to provide early notification if something is amiss. Instead of immediately launching a process improvement effort to determine whether special causes are present, the Quality Engineer may temporarily increase the rate at which samples are taken from the process output until it's clear that the process is truly in control. Note that with three sigma limits, one expects to be signaled approximately once out of every 370 points on average, just due to common-causes.

Choice of limits

Shewhart set 3-sigma (3-standard error) limits on the following basis.

Shewhart summarized the conclusions by saying:

... the fact that the criterion which we happen to use has a fine ancestry in highbrow statistical theorems does not justify its use. Such justification must come from empirical evidence that it works. As the practical engineer might say, the proof of the pudding is in the eating.

Though he initially experimented with limits based on probability distributions, Shewhart ultimately wrote:

Some of the earliest attempts to characterize a state of statistical control were inspired by the belief that there existed a special form of frequency function f and it was early argued that the normal law characterized such a state. When the normal law was found to be inadequate, then generalized functional forms were tried. Today, however, all hopes of finding a unique functional form f are blasted.

The control chart is intended as a heuristic. Deming insisted that it is not a hypothesis test and is not motivated by the Neyman-Pearson lemma. He contended that the disjoint nature of population and sampling frame in most industrial situations compromised the use of conventional statistical techniques. Deming's intention was to seek insights into the cause system of a process ...under a wide range of unknowable circumstances, future and past .... He claimed that, under such conditions, 3-sigma limits provided ... a rational and economic guide to minimum economic loss... from the two errors:

  1. Ascribe a variation or a mistake to a special cause when in fact the cause belongs to the system (common cause). (Also known as a Type I error)
  2. Ascribe a variation or a mistake to the system (common causes) when in fact the cause was special. (Also known as a Type II error)

Calculation of standard deviation

As for the calculation of control limits, the standard deviation (error) required is that of the common-cause variation in the process. Hence, the usual estimator, in terms of sample variance, is not used as this estimates the total squared-error loss from both common- and special-causes of variation.

An alternative method is to use the relationship between the range of a sample and its standard deviation derived by Leonard H. C. Tippett, an estimator which tends to be less influenced by the extreme observations which typify special-causes.

Rules for detecting signals

The most common sets are:

There has been particular controversy as to how long a run of observations, all on the same side of the centre line, should count as a signal, with 7, 8 and 9 all being advocated by various writers.

The most important principle for choosing a set of rules is that the choice be made before the data is inspected. Choosing rules once the data have been seen tends to increase the Type I error rate owing to testing effects suggested by the data.

Alternative bases

In 1935, the British Standards Institution, under the influence of Egon Pearson and against Shewhart's spirit, adopted control charts, replacing 3-sigma limits with limits based on percentiles of the normal distribution. This move continues to be represented by John Oakland and others but has been widely deprecated by writers in the Shewhart-Deming tradition.

Performance of control charts

When a point falls outside of the limits established for a given control chart, those responsible for the underlying process are expected to determine whether a special cause has occurred. If one has, then that cause should be eliminated if possible. It is known that even when a process is in control (that is, no special causes are present in the system), there is approximately a 0.27% probability of a point exceeding 3-sigma control limits. Since the control limits are evaluated each time a point is added to the chart, it readily follows that every control chart will eventually signal the possible presence of a special cause, even though one may not have actually occurred. For a Shewhart control chart using 3-sigma limits, this false alarm occurs on average once every 1/0.0027 or 370.4 observations. Therefore, the in-control average run length (or in-control ARL) of a Shewhart chart is 370.4.

Meanwhile, if a special cause does occur, it may not be of sufficient magnitude for the chart to produce an immediate alarm condition. If a special cause occurs, one can describe that cause by measuring the change in the mean and/or variance of the process in question. When those changes are quantified, it is possible to determine the out-of-control ARL for the chart.

It turns out that Shewhart charts are quite good at detecting large changes in the process mean or variance, as their out-of-control ARLs are fairly short in these cases. However, for smaller changes (such as a 1- or 2-sigma change in the mean), the Shewhart chart does not detect these changes efficiently. Other types of control charts have been developed, such as the EWMA chart and the CUSUM chart, which detect smaller changes more efficiently by making use of information from observations collected prior to the most recent data point.

Criticisms

Several authors have criticised the control chart on the grounds that it violates the likelihood principle. However, the principle is itself controversial and supporters of control charts further argue that, in general, it is impossible to specify a likelihood function for a process not in statistical control, especially where knowledge about the cause system of the process is weak.

Some authors have criticised the use of average run lengths (ARLs) for comparing control chart performance, because that average usually follows a geometric distribution, which has high variability and difficulties

Types of charts

Chart Process observation Process observations relationships Process observations type Size of shift to detect
XbarR chart Quality characteristic measurement within one subgroup Independent Variables Large (≥ 1.5σ)
XbarS chart Quality characteristic measurement within one subgroup Independent Variables Large (≥ 1.5σ)
Shewhart individuals control chart (ImR chart or XmR chart) Quality characteristic measurement for one observation Independent Variables Large (≥ 1.5σ)
Three-way chart Quality characteristic measurement within one subgroup Independent Variables Large (≥ 1.5σ)
p-chart Fraction nonconforming within one subgroup Independent Attributes Large (≥ 1.5σ)
np-chart Number nonconforming within one subgroup Independent Attributes Large (≥ 1.5σ)
c-chart Number of nonconformances within one subgroup Independent Attributes Large (≥ 1.5σ)
u-chart Nonconformances per unit within one subgroup Independent Attributes Large (≥ 1.5σ)
EWMA chart Exponentially weighted moving average of quality characteristic measurement within one subgroup Independent Attributes or variables Small (< 1.5σ)
CUSUM chart Cumulative sum of quality characteristic measurement within one subgroup Independent Attributes or variables Small (< 1.5σ)
Time series model Quality characteristic measurement within one subgroup Autocorrelated Attributes or variables N/A
Regression Control Chart Quality characteristic measurement within one subgroup Dependent of process control variables Variables Large (≥ 1.5σ)

See also

Notes

  1. ^ Western Electric - A Brief History
  2. ^ "Why SPC?" British Deming Association SPC Press, Inc. 1992
  3. ^ Wheeler, Donald J.; Chambers, David S. (1992), Understanding statistical process control (2 ed.), Knoxville, Tennessee: SPC Press, p. 96, ISBN 9780945320135, OCLC 27187772 

Bibliography

  • Deming, W E (1975) "On probability as a basis for action." The American Statistician. 29(4), pp146-152
  • Deming, W E (1982) Out of the Crisis: Quality, Productivity and Competitive Position ISBN 0-521-30553-5.
  • Mandel, B J (1969). "The Regression Control Chart" Journal of Quality Technology. 1 (1), pp 1-9.
  • Oakland, J (2002) Statistical Process Control ISBN 0-7506-5766-9.
  • Shewhart, W A (1931) Economic Control of Quality of Manufactured Product ISBN 0-87389-076-0.
  • Shewhart, W A (1939) Statistical Method from the Viewpoint of Quality Control ISBN 0-486-65232-7.
  • Wheeler, D J (2000) Normality and the Process-Behaviour Chart ISBN 0-945320-56-6.
  • Wheeler, D J & Chambers, D S (1992) Understanding Statistical Process Control ISBN 0-945320-13-2.
  • Wheeler, Donald J. (1999). Understanding Variation: The Key to Managing Chaos - 2nd Edition. SPC Press, Inc. ISBN 0-945320-53-1.

External links

Note: Before adding your company's link, please read WP:Spam#External_link_spamming and WP:External_links#Links_normally_to_be_avoided.

 
 

 

Copyrights:

Sci-Tech Dictionary. McGraw-Hill Dictionary of Scientific and Technical Terms. Copyright © 2003, 1994, 1989, 1984, 1978, 1976, 1974 by McGraw-Hill Companies, Inc. All rights reserved.  Read more
Sci-Tech Encyclopedia. McGraw-Hill Encyclopedia of Science and Technology. Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.  Read more
Accounting Dictionary. Dictionary of Accounting Terms. Copyright © 2005 by Barron's Educational Series, Inc. All rights reserved.  Read more
Wikipedia. This article is licensed under the Creative Commons Attribution/Share-Alike License. It uses material from the Wikipedia article "Control chart" Read more