
[After Henry Laurence Gantt (1861-1919), American engineer.]
A graphic device that depicts tasks, machines, personnel, or whatever resources are required to accomplish a job on a calendar-oriented grid. Charts may be provided for various managerial levels and responsibilities, but detailed planning occurs at the lowest organizational level. Performance may be monitored and controlled throughout the organization.
The Gantt chart is an effective tool for planning and scheduling operations involving a minimum of dependencies and interrelationships among the activities. The technique is best applied to activities for which time durations are not difficult to estimate, since there is no provision for treatment of uncertainty. On the other hand, the charts are easy to construct and understand, even though they may contain a great amount of information. In general, the charts are easily maintained provided the task requirements are somewhat static.
An initial step in development of a Gantt chart may be to specify the tasks or activities making up a project, as shown in the illustration. The amount of time required for each activity is represented as a horizontal bar on the chart, with open triangles designating original start and finish dates in this example. The open start triangle is changed to a filled triangle upon inauguration of the activity, and the bar is filled in with vertical lines to indicate progress and completion. The open finish triangle is also filled upon completion. Slippage times are documented on the chart by broken lines, and the diamond symbols are employed to indicate rescheduled work. The vertical line on the chart is the current-date indicator and indicates present and future status of the project as of that date.

Example of a Gantt bar chart.
Updating of a Gantt chart will reveal difficulties encountered in the conduct of a project. Possible solutions include rescheduling, overtime, multishift operations, use of additional equipment and facilities, and changes in method.
An outgrowth of the bar chart technique is the milestone chart. A milestone is an important activity in the sequence of project completion. The most significant activities may be designated major milestones. The primary difference in this concept is the graphic display, since the method and collection of data are the same. The milestone approach offers no intrinsic improvement over the basic Gantt chart but provides a means for focusing resources on critical items. See also PERT.
A type of floating bar chart usually used in project management to show resources or tasks over time.
Download Computer Desktop Encyclopedia to your PC, iPhone or Android.
| Gaming, Gallup Poll, Galloping Inflation | |
| Gap Loan, Garden Apartments, Garnish |
A Gantt chart is a visual representation of a project schedule. A type of bar chart, a Gantt charts show the start and finish dates of the different required elements of a project. Henry Laurence Gantt, an American mechanical engineer, is recognized for developing the Gantt chart.
Investopedia Says:
Gantt charts are useful in planning how long a project should take and helping to sequence the events by laying them out in the order in which the tasks need to be completed.
Typically, tasks are shown on the vertical axis, and the project time span is represented on the horizontal axis. Each task has a corresponding bar that shows the time span required for that task. The bar can be filled in to show the percentage of the task that has been completed. Gantt charts also indicate dependencies, those tasks that are dependent upon other tasks. Today there are many software applications available for creating Gantt charts, as well as functions in popular programs such a Microsoft Excel.
Related Links:
Swimming in a sea of numbers? Find out how to crunch them quickly! Microsoft Excel Features For The Financially Literate
Momentum can be used with other tools to be an effective buy/sell indicator. Momentum Indicates Stock Price Strength
Take a closer look at this indicator, which during a trending period, is a very useful and accurate tool. Introduction To The Parabolic SAR
Discover the components and basic patterns of this ancient technical analysis technique. Candlestick Charting: What Is It?
Enhance trend isolation and prediction of future prices with this technique. Heikin-Ashi: A Better Candlestick
This technique can reduce uncertainty in estimating future outcomes. Bet Smarter With The Monte Carlo Simulation
A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e., precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line as shown here.
Although now regarded as a common charting technique, Gantt charts were considered revolutionary when first introduced[citation needed]. In recognition of Henry Gantt's contributions, the Henry Laurence Gantt Medal is awarded for distinguished achievement in management and in community service. This chart is also used in Information Technology to represent data that has been collected.
|
Contents
|
The first known tool of this type was reportedly developed in 1896 by Karol Adamiecki, who called it a harmonogram. Adamiecki only published his chart in 1931, however, in Polish, which limited both its take-up and recognition of his authorship. The chart is named after Henry Gantt (1861–1919), who designed his chart around the years 1910–1915.[1][2]
One of the first major applications of Gantt charts was during the First World War. On the initiative of General William Crozier, then Chief of Ordnance these included that of the Emergency Fleet, the Shipping Board, etc.[3]
In the 1980s, personal computers allowed for widespread creation of complex and elaborate Gantt charts. The first desktop applications were intended mainly for project managers and project schedulers. With the advent of the Internet and increased collaboration over networks at the end of the 1990s, Gantt charts became a common feature of web-based applications, including collaborative groupware.
Gantt charts have become a common technique for representing the phases and activities of a project work breakdown structure (WBS), so they can be understood by a wide audience all over the world.
A common error made by those who equate Gantt chart design with project design is that they attempt to define the project work breakdown structure at the same time that they define schedule activities. This practice makes it very difficult to follow the 100% Rule. Instead the WBS should be fully defined to follow the 100% Rule, then the project schedule can be designed.[4]
Although a Gantt chart is useful and valuable for small projects that fit on a single sheet or screen, they can become quite unwieldy for projects with more than about 30 activities[citation needed]. Larger Gantt charts may not be suitable for most computer displays. A related criticism is that Gantt charts communicate relatively little information per unit area of display. That is, projects are often considerably more complex than can be communicated effectively with a Gantt chart.
Gantt charts only represent part of the triple constraints (cost, time and scope) of projects, because they focus primarily on schedule management. Moreover, Gantt charts do not represent the size of a project or the relative size of work elements, therefore the magnitude of a behind-schedule condition is easily miscommunicated. If two projects are the same number of days behind schedule, the larger project has a larger impact on resource utilization, yet the Gantt does not represent this difference.
Although project management software can show schedule dependencies as lines between activities, displaying a large number of dependencies may result in a cluttered or unreadable chart.
Because the horizontal bars of a Gantt chart have a fixed height, they can misrepresent the time-phased workload (resource requirements) of a project, which may cause confusion especially in large projects. In the example shown in this article, Activities E and G appear to be the same size, but in reality they may be different orders of magnitude. A related criticism is that all activities of a Gantt chart show planned workload as constant. In practice, many activities (especially summary elements) have front-loaded or back-loaded work plans, so a Gantt chart with percent-complete shading may actually miscommunicate the true schedule performance status.
In the following example there are seven tasks, labeled A through G. Some tasks can be done concurrently (A and B) while others cannot be done until their predecessor task is complete (C cannot begin until A is complete). Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic time estimate (P). The expected time (TE) is computed using the beta probability distribution for the time estimates, using the formula (O + 4M + P) ÷ 6.
| Activity | Predecessor | Time estimates | Expected time | ||
|---|---|---|---|---|---|
| Opt. (O) | Normal (M) | Pess. (P) | |||
| A | — | 2 | 4 | 6 | 4.00 |
| B | — | 3 | 5 | 9 | 5.33 |
| C | A | 4 | 5 | 7 | 5.17 |
| D | A | 4 | 6 | 10 | 6.33 |
| E | B, C | 4 | 5 | 7 | 5.17 |
| F | D | 3 | 4 | 8 | 4.50 |
| G | E | 3 | 5 | 8 | 5.17 |
Once this step is complete, one can draw a Gantt chart or a network diagram.
| Wikimedia Commons has media related to: Gantt charts |
This entry is from Wikipedia, the leading user-contributed encyclopedia. It may not have been reviewed by professional editors (see full disclaimer)