SPI, in Project Management Terms, is short for Schedule
Performance Index. It's an indicator on whether the Project is on
Schedule (SPI = 1), Ahead of Schedule (SPI > 1), or behind
Schedule (SPI < 1).
View page
In-spi-ra-tion.
View page
SPI stands for Schedule Performance Index.
SPI is a measure of the schedule efficiency of a project
calculated by dividing earned value (EV) by planned value (PV).