Convert the measurement in square feet to square yards and the thickness in inches to yards.
3 feet = 1 yard
9 square feet = 1 square yard. : 1100 square feet = 1100/9 = 122.2222 sq yards
36 inches = 1 yard
5 inches = 5/36 = 0.13888 yards.
The amount of concrete required = 122.2222 x 0.13888 = 16.975 cubic yards
In practice, an order would be sent for 17 cubic yards of concrete.
1,100 sq ft = 122.22 sq yds 6 inches = 0.166 yds Thus the volume = 122.22 x 0.166 = 20.37 cubic yards
You need just over 7 cubic yards of concrete. The volume you want to fill is 190 cubic feet. A cubic yard is 27 cubic feet. 190 divided by 27 is 7.037
Basic maths... 63.33 cubic yards.
6.67 Cubic Yards
If it is 4 inches deep/thick, 2 cubic yards. If it is 6 inches deep/thick, 3 cubic yards.
39.1116 cubic yards
50x100x4 = 20,000 cubic inches36 inches in a yard20,000/36 = 555 5/9 cubic yards.
Depends on how thick it is. At 4 inches thick, you would nee about 5.5 cubic yards adjusting for safety. At 6 inches, you'd need about 8 cubic yards. You can play with different thicknesses with the linked concrete pad calculator.
15 cubic yards
15 cubic yards
8.25 cubic yards of concrete
30.81 cubic yards
151/9 cubic yards for every 12 inches thick
It depends upon how thick you want the concrete. For example, if you want the concrete to be 6 inches thick, then you will need 200 cubic feet. There are 27 cubic feet per cubic yard; so divide the 200 cubic feet by 27 to get 7.4 cubic yards.
9.3 cubic yards of cement is required for this slab.