18.6765 cubic blathinetres is one brass
How much cement sand and stone do you need for 1 cubic meter of concre
Type your answer here... 11.2
1:6 brick work sand consumption for 1 cubic meter = 9.71 cft 1 cubic meter brick work cement consumption = 1.32 bags 1.32/28.8= .0458 cubic meter .458*6 = .275 .275*35.31 =9.71 cft
1 cubic foot=100 lbs of sand 1728 cubic in.=100 lbs of sand 864 cubic in.= 50 lbs of sand 432 cubic in.= 25 lbs of sand and so on and so on
The Question is mistake. The Question is How much sand and aggregate required for the one cubic meter of M20 grade concrete? Answer :- 20mm aggregate = 0.90M3 Sand = 0.45M3 to 0.5M3 depond on the Bulk density of Sand Cement = 320kg
How much cement sand and stone do you need for 1 cubic meter of concre
100 Cubic feet of sand is one brass a Truck load is about 2.5 Brass of sand Brass is old unit, generally used in construction in India
1 cm cubed or 1cm3
100
The weight varies; but if it's dry sand, the cubic meter will weigh around 1500 kilos.
The word "brass" refers to a measure of quantity for loose material (like sand, metal, etc). This term is common in India. One brass equals one hundred cubic feet volume. Calculate the volume of sand and divide by 100 cubic feet to get the number of brass units.
3 cubic meter
80
3
Concrete is a mixture of cement, sand, stone, and water. In a cuibic meter of concrete, , there is about 0.3 cubic meters of sand, or about 475 kg
With dry sand. 1.602 tonnes
Type your answer here... 11.2