The longest route through a series of interrelated tasks. Should a task on the critical path slip then the end date of the project would be jeopardized.

Critical Path

Most projects contain a large number of tasks. The critical path is the order of tasks that must be finished for the project to be considered complete. This path dictates the final finish date of your project plan.

The critical path is not primarily a list of vital tasks. It is a specific sequence of tasks, each task depending on the last.

As the project progresses, different sequences might be named as critical. Consider a project with two vital task sequences which we'll call selecting the new office site and Moving in to new offices. At the onset, the first task is projected to take 9 months and the second is projected to take 6 months. Since the first task will take longer and is deemed as being on the critical path.

After three months work, should the first task perform ahead of schedule with a new estimate of 5 additional months more while the second has been delayed by three moths the latter task would now be on the critical path?

What is a Critical Task

The definition of a critical task is any task that with a change of duration may positively or negatively affect the end date of the project if delayed

Tracking the Critical Path

The Gantt chart and network diagram two classic views in MS Project will display critical tasks and links in red automatically to make these tasks easier to observe and report.

Slack Time

Total slack is the amount of time that lies off the critical path. In other words changes to the duration of these tasks may or may not affect the critical path.

Slack is the amount of time a task can be delayed and still be on schedule. A 5 day task with a 10 day deadline has 5 days of slack. A task with no slack is automatically critical. Imagine two tasks due to finish at the same time. Packing computer equipment with one day of duration and packing files with four days duration. If they both started at the same time the pack equipment tasks would have three days of slack.

http://www.mousetraining.co.uk/training-manuals/Project2007.pdf for a training manual and quick key card

User Avatar

Wiki User

14y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What a critical path in a project is and how it is determined?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Continue Learning about Management

Critical path of a project?

The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


Why is it important to determine the critical path of a project?

The critical path helps you in determining how to accelerate your project by compressing tasks. Putting more people on critical path tasks and finishing it earlier will shorten the duration of the project (this is called crashing).


What are the uses of the critical path?

These critical path enables PMs to know which activities (tasks) are essential for Project Completion (can delay the project), and which activities are not. It also gives a clear idea on how to accelerate the projects (eg by adding more resources to the tasks on the critical path).Answer:Critical Path Method: This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


Why critical path is critical to project management?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start dateThe Critical Path and Duration of the Critical Path, gives the project manager a clear picture of how long all the activities can take to complete. It also helps him to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.


What is the purpose of critical path analysis?

The purpose of critical path analysis is to become an important tool which will give your project an effective management by scheduling a set of project activities.

Related questions

Why is critical path the longest path?

As per the Project Management Terminology, the longest path in a project sequence of activities is called the Critical Path. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date. Since this path is going to determine the schedule/delivery date of the project, it is called the critical path.


Critical path of a project?

The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


What is defined by a critical path?

The Critical Path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date. Critical Path is one of the key outputs of the Project Schedule Creation activity


Why is it important to determine the critical path of a project?

The critical path helps you in determining how to accelerate your project by compressing tasks. Putting more people on critical path tasks and finishing it earlier will shorten the duration of the project (this is called crashing).


What is critical path?

In Project Management the Critical Path is the series of tasks that must finish on time for the entire project to finish on schedule. Each task on the critical path is a time critical task. You can also think of it as:the longest path from start to finishor the path without any slack,the path corresponding to the shortest time in which the project can be completed.


How do you explain the critical path analysis?

Critical path analysis is a project management technique used to identify the longest sequence of activities in a project, also known as the critical path. It helps to determine the minimum time required to complete a project by identifying the activities that have no flexibility in their schedule. By focusing on the critical path, project managers can prioritize resources and ensure that any delays or changes on these activities will directly impact the project's overall timeline.


What are the uses of the critical path?

These critical path enables PMs to know which activities (tasks) are essential for Project Completion (can delay the project), and which activities are not. It also gives a clear idea on how to accelerate the projects (eg by adding more resources to the tasks on the critical path).Answer:Critical Path Method: This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


Why critical path is critical to project management?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start dateThe Critical Path and Duration of the Critical Path, gives the project manager a clear picture of how long all the activities can take to complete. It also helps him to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.


What is the importance of critical path and critical task estimation?

The importance of the Critical path is that helps you in reducing risk, contingency planning, and project planning.


What is the purpose of critical path analysis?

The purpose of critical path analysis is to become an important tool which will give your project an effective management by scheduling a set of project activities.


'project control should always focus on the critical path' comment?

Not necessarily. Critical path analysis determines the longest path through a network of project activities, because the main purpose of understanding the critical path is to focus effort on activities that lie on this path, thus increasing the chances of finishing the project on time. If you solely only focus on the critical path activities, then chances are that the activities not on the critical path will soon be on the new critical path because you haven't taken sufficient time to focus on all the activities. Project control should focus on the project as a whole, however more emphasis can be placed on the critical path activities as well as any risky/uncertain activities that could (if not monitored closely) eventually become a critical path activity and push the end date out even further.


What is the significance of Critical Path Analysis in Project development?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date.The second important feature of the critical path method is to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.Without a proper Critical Path Analysis, an efficient Schedule for the Project cannot be created