A level 3 schedule in planning is one of the 5 levels is common use. Level 1 is the "highest" and shows the main milestones to complete the project. Level 2 shows the scope of work to achieve the milestones, Level 3 shows the deliverables to achieve the scope of work, these three levels are the summary levels. Level 4 shows the tasks or work packs needed to complete the deliverables, and at level 5 the tasks will be fully resourced. A Level 1 is typically 1 or 2 pages, Level 2 around 50 activities, Level 3 about 250. Level 5 on a large project will be many thousands of activities.

User Avatar

Wiki User

15y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is Level 3 schedule in planning?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What is level 3 project schedule?

Level 3 project schedule is the maximum level of granularity to decompose your WBS into. Here's an example: 1 PROJECT 1.2 Design 1.2.1 Conceptual Design 1.2.1 (conceptual design) is a level 3 element.


What is a level 4 project schedule?

level-4 schedule is deliverable level schedule


What does the activities during the planning include?

Project Planning involves 4 important phases. They are: 1. Planning the Project Scope 2. Planning the Project Resources 3. Planning the Project Schedule 4. Planning Quality & Risk Management


Three main activities involved in project planning?

Project Planning involves 4 important phases. They are: 1. Planning the Project Scope 2. Planning the Project Resources 3. Planning the Project Schedule 4. Planning Quality & Risk Management


What is an important element in the project planning?

Project Planning involves 4 important phases. They are: 1. Planning the Project Scope 2. Planning the Project Resources 3. Planning the Project Schedule 4. Planning Quality & Risk Management Each of these 4 phases is equally important and have a significant impact on the success of the project


What are the issues in menu planning?

Set a schedule and meals for the week and do the dishes.


What is a mock schedule?

A mock schedule is a simulated or trial version of a schedule that is used for planning, testing, or practice purposes. It allows individuals or teams to visualize how tasks or events will be organized without committing to a final schedule. Mock schedules are often used in project management, event planning, and academic settings.


Explain in brief meaning and scope of grassroots level planning?

Grassroots level planning may be defined as the form of planning lower institutional levels.


Is the master production schedule is developed drectly from the capacity requirements planning?

true


What are the components of planning in the management?

Planning in a management position may include writing the schedule for when employees will work. Planning may also involve events, specials, and how to spend money in the business.


Explain the significance and issues in micro level planning?

importance of micro planning


What schedule is Tylenol 3?

Schedule 4 drug