PERT(Program Evaluation and Review Technique) | CPM (Critical Path Method)
_____________________________________ | ______________________________________
1)PERT is a probabilistic tool used with three 1)CPM is a deterministic tool, with only single
Estimating the duration for completion of estimate of duration.
activities.
_______________________________________________________________________________
2)This tool is basically a tool for planning 2)CPM also allows and explicit estimate of
and control of time. costs in addition to time, therefore CPM can
control both time and cost.
_______________________________________________________________________________
3)PERT is more suitable for R&D related 3)CPM is best suited for routine and those
projects where the project is performed for projects where time and cost estimates can
the first time and the estimate of duration be accurately calculated.
are uncertain.
_______________________________________________________________________________
4)The probability factor i major in PERT 4)The deterministic factor is more so values or
so outcomes may not be exact. outcomes are generally accurate and
realistic.
_______________________________________________________________________________
Extensions of both PERT and CPM allow the user to manage other resources in addition to time and money, to trade off resources, to analyze different types of schedules, and to balance the use of resources.tensions of both PERT and CPM allow the user to manage other resources in addition to time and money, to trade off resources, to analyze different types of schedules, and to balance the use of resources.
PERT/CPM suffers mainly suffers from a main issue is that when the network becomes very big (eg containing hundreds of activities) it becomes almost impossible to handle (printing, reading, etc...). Comparing CPM to CCPM we discover that CCPM has a better utilization of project resources, among other advantages.
Gantt chart is a tool which is useful in scheduling the various activities of a project in the form of horizontal bar graph where as CPM provides a graphical view and network of events and activities in chronological manner.
PERT chart is a technique for scheduling a project based on individual tasks or activities whereas Gantt Chart is a bar chart that represents the tasks and activities of the project schedule.Source: Satzinger, J., Jackson, R., Burd, S. "Systems Analysis and Design in a changing world" Fifth Edition, Cengage Learning, Boston.
1.identification of component 2.sequencing of activities and event 3.time analysis 4.determination of critical path 4.modification in initial path 5.controlling the project
CPM is a term in advertising which stands for cost per mile. But it is basically about the cost per thousand impression or view. CPM are specifically targeted at advertisers that want others to view their advertisement. In CPM ad networks, advertisers pay for the amount of traffic that simply views the advertisement. CPM advertising comes in various forms. Banner ads, popup, popunder are some of the popular kinds of CPM advertising model.
Both are used for planning and scheduling. Steps to create both networks are similar
kamil_ka@list.ru
CPM -Critical Path Method
Program Evaluation and Review Technique (PERT) lays the foundation of the network diagram or process by which the program will be completed. The Critical Path Method (CPM) is used within PERT to determine a critical path for a project within a program or the program itself if all the duration information is known for the program. CPM is a subset of PERT.
Critical Path Method (CPM) - A schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram.
Program Evaluation and Review Technique: is a network technique that uses three times estimates for each activity in a project. PERT is probalistic, whereas CPM is deterministic.
Yes, CPM software is available on the internet. 3d2f.com/tags/cpm/pert/ is a website with free CPM softward downloads. Yes, CPM software is available on the internet. There are many different companies that provide the software at different prices. You can look at the various places to see what requirements you need.
Statistical Control Reports Break Even Analysis PERT CPM
If the abbreviations stand for cycles per minute and revolutions per minute, there is no difference.
PERT/CPM suffers mainly suffers from a main issue is that when the network becomes very big (eg containing hundreds of activities) it becomes almost impossible to handle (printing, reading, etc...). Comparing CPM to CCPM we discover that CCPM has a better utilization of project resources, among other advantages.
R. D. Archibald has written: 'Network-based management systems (PERT/CPM)'
Joseph J. Moder has written: 'Project management with CPM, PERT, and precedence diagramming' -- subject(s): Critical path analysis, PERT (Network analysis), Project management