The master production schedule “drives” the system. It states the planned due dates for end items. Material requirements planning computer runs, however, involve an iterative process. The master production schedule “proposes” or “hypothesizes” a tentative schedule. After the MRP run with this schedule, the shop scheduler examines the MRP plan for impractical loads on the productive system—either by stating excessive demands on personnel or equipment, or in excessive idle time. Then the master production schedule is revised and the program is run again.

User Avatar

Wiki User

12y ago

What else can I help you with?

Continue Learning about Accounting

What is a Master Production Schedule?

Master Production Schedule or MPS is the production plan company establishes for specific fiscal year for producing goods as well as for inventory, staffing etc to meet the required sales demand for specific period.


MRP is more than an inventory system.What additional capabilities does MRP possess?

Materials resource planning (MRP) is a system that uses bill-of-material, current inventory levels, expected receipts of inventory, and a master production schedule to determine material requirements. When MRP is used correctly a manufacturing company will have the right inventory on hand at the correct time to ensure the master production schedule will be fulfilled.


What is an example of a master budget?

A manufacturing organization's master budget includes a production budget, which uses the sales budget and inventory levels anticipated at the beginning and end of the period to determine how much to produce.


What is the first budge prepared as part of a master budget?

The first budget prepared as part of a master budget is typically the sales budget. This budget outlines projected sales in units and dollars for a specific period, serving as the foundation for other budgets, such as production, inventory, and cash budgets. Accurate sales forecasting is crucial, as it influences the overall financial planning and resource allocation for the organization.


Where can one find a master accounting service?

One can find a master accounting service by using the Master Accounting service website which offers complete information on the master accounting service.

Related Questions

What is a Master Production Schedule?

Master Production Schedule or MPS is the production plan company establishes for specific fiscal year for producing goods as well as for inventory, staffing etc to meet the required sales demand for specific period.


What is the main purpose of master production schedule?

matching output to customer demand


Is the master production schedule is developed drectly from the capacity requirements planning?

true


Distinguish between the aggregate plan and master production scheduel?

The aggregate plan outlines a company's overall production strategy for a specific period, balancing supply and demand while considering resources, capacity, and inventory levels. In contrast, the master production schedule (MPS) breaks down the aggregate plan into specific production activities, detailing what products need to be made, in what quantities, and when they should be completed. Essentially, the aggregate plan provides a high-level overview, while the MPS offers a more granular, actionable schedule for production.


What was the Production Budget for The Master?

The Production Budget for The Master was $37,500,000.


What is an input to the master production schedule?

An input to the master production schedule (MPS) includes forecasts of customer demand, which help determine the quantity and timing of products needed. Additionally, current inventory levels and production capacities play a crucial role in shaping the MPS. Other factors may include lead times for materials and components, as well as any planned promotions or seasonal fluctuations in demand. This comprehensive information ensures that production aligns with both market needs and operational capabilities.


What is the purpose of a master production schedule?

A master production schedule (MPS) outlines what products need to be produced, in what quantities, and when they should be completed. It serves as a key planning tool that aligns production with demand forecasts, helping to optimize resource allocation and inventory management. By providing a clear timeline and objectives, the MPS ensures that manufacturing operations run efficiently and meet customer delivery expectations. Overall, it helps organizations balance supply and demand effectively.


MRP is more than an inventory system.What additional capabilities does MRP possess?

Materials resource planning (MRP) is a system that uses bill-of-material, current inventory levels, expected receipts of inventory, and a master production schedule to determine material requirements. When MRP is used correctly a manufacturing company will have the right inventory on hand at the correct time to ensure the master production schedule will be fulfilled.


What is the relationship between aggregate planning and master production schedule?

The aggregate plan balances the Plant's capacity with demand and the MPS translates this plan into numbers of specific products in time frames.


Where can I inquire about masters degree counseling?

When you are applying for a master's program, it is frequently the case that a guidance counselor will schedule a session to discuss your career and education goals. Master's programs tend to be fairly competitive, and the counselor wants to protect the school's interests by making sure that they are accepting students into the program that will complete their degrees.


How do you get the master schedule from marauder on epic duel?

plz tell me the answer


What is the correct sequence of mps mrp the production plan and pac?

The correct sequence is: Master Production Schedule (MPS), then Material Requirements Planning (MRP), followed by the production plan, and finally the Production Activity Control (PAC). The MPS outlines what needs to be produced and when, which informs the MRP to determine the materials required. The production plan is developed based on this information, guiding the overall manufacturing strategy. Lastly, PAC manages and controls the execution of the production plan on the shop floor.