answersLogoWhite

0

6 x 4.32 = 25.92 so you will need 26 bags. You might want to get up to 10 % extra for waste.

User Avatar

Wiki User

13y ago

What else can I help you with?

Continue Learning about Basic Math

how many bags of cement needed to mix slab 14 by 11 4 inchesHow many bags of portland cement is needed to mix 1 cubic yds?

To calculate the number of bags of cement needed for a slab measuring 14 feet by 11 feet and 4 inches thick, first convert the dimensions to cubic yards. The volume is approximately 4.58 cubic yards. Generally, one cubic yard of concrete requires about 5 to 6 bags of Portland cement, so you would need approximately 23 to 27 bags of cement for this slab.


5x7 4 inches thick how many 80 lb bags of cement will it take?

To determine how many 80 lb bags of cement are needed for a 5x7 area that is 4 inches thick, first calculate the volume in cubic feet. The volume is 5 ft × 7 ft × (4/12) ft = 11.67 cubic feet. An 80 lb bag of cement typically covers about 0.6 cubic feet, so you would need approximately 20 bags of cement (11.67 ÷ 0.6 ≈ 19.45). Therefore, you would need 20 bags to complete the project.


How many bags of cement to make 1cubic meter of concrete for M15grade nominal mix?

In an M15 grade nominal mix, the typical ratio is 1:2:4 (cement:sand:aggregate). For 1 cubic meter of concrete, you would generally need about 7 bags of cement, as one bag of cement weighs 50 kg and approximately 0.035 cubic meters of cement is used. Therefore, the total quantity of cement needed for 1 cubic meter of M15 concrete is around 350 kg, which translates to about 7 bags.


How many bags of portland cement is needed to mix 1 cubic yard?

To mix 1 cubic yard of concrete, you typically need about 5 to 6 bags of Portland cement, depending on the specific mix design and the desired strength of the concrete. A standard 94-pound bag of Portland cement yields roughly 0.5 cubic feet when mixed. Therefore, for 1 cubic yard (27 cubic feet), approximately 5.7 bags would be required. Always check the specific mix requirements for your project, as variations can occur.


How many bags of pre-mix cement is needed to mix 1 cubic yds?

Cement comes in bags that weigh 94 lbs. The volume of the bag is approximately 1 cubic foot. If you want to mix concrete which is a mixture of a coarse aggregate (gravel) and a fine aggregate (sand) and something to bond the two aggregates together (cement) then firstly you need to know the strength concrete that you require. For 1 cubic yard of 3000psi (pounds per square inch) strength you will need about 6 bags cement 12 cubic feet of sand and 24 cubic feet of gravel. Rule of thumb is the ratio should be 1:2:4 (cement:sand:gravel)

Related Questions

How many 60lb bags of cement in yard of cement?

There are 27 cubic feet in a cubic yard, and a 60-pound bag of cement typically yields about 0.45 cubic feet when mixed. To fill one cubic yard, you would need approximately 60 bags of 60-pound cement.


how many bags of cement needed to mix slab 14 by 11 4 inchesHow many bags of portland cement is needed to mix 1 cubic yds?

To calculate the number of bags of cement needed for a slab measuring 14 feet by 11 feet and 4 inches thick, first convert the dimensions to cubic yards. The volume is approximately 4.58 cubic yards. Generally, one cubic yard of concrete requires about 5 to 6 bags of Portland cement, so you would need approximately 23 to 27 bags of cement for this slab.


5x7 4 inches thick how many 80 lb bags of cement will it take?

To determine how many 80 lb bags of cement are needed for a 5x7 area that is 4 inches thick, first calculate the volume in cubic feet. The volume is 5 ft × 7 ft × (4/12) ft = 11.67 cubic feet. An 80 lb bag of cement typically covers about 0.6 cubic feet, so you would need approximately 20 bags of cement (11.67 ÷ 0.6 ≈ 19.45). Therefore, you would need 20 bags to complete the project.


What is the number of bags of cement required for 1 cubic meter of M25 grade cement?

For M25 grade concrete, the mix proportion is typically 1:1:2 (cement:sand:aggregate). This means for 1 cubic meter of concrete, you would need 1/4 cubic meter of cement. As 1 cubic meter is equivalent to 35.32 cubic feet, and one bag of cement usually covers around 0.035 cubic meters, you would need approximately 7-8 bags of cement for 1 cubic meter of M25 grade concrete.


How many bags of cement to make 1cubic meter of concrete for M15grade nominal mix?

In an M15 grade nominal mix, the typical ratio is 1:2:4 (cement:sand:aggregate). For 1 cubic meter of concrete, you would generally need about 7 bags of cement, as one bag of cement weighs 50 kg and approximately 0.035 cubic meters of cement is used. Therefore, the total quantity of cement needed for 1 cubic meter of M15 concrete is around 350 kg, which translates to about 7 bags.


How many 20 kg bags of cement will you need to mix with 13 cubic meters of sand if you want to mix at a ratio of 8 sand to 1 cement?

If a 20kg bag of cement=0.1m3 with 100 lots o 0.01 to 1m3 then you will need 12.5 bags per m3. So you need approx 11.5m3 of sand and 144 bags of cement (144 x 0.01 = 1.44m3) to give you a total of 12.94m3


How many 50-kilo-bags of cement is needed to fill 102.16 cubic feet. Area is 9.5 meters by 3 meters?

1 50kg bag fill about 2 cubic f. so for 102cu.f. you'll need 51 bags


How many bags of portland cement is needed to mix 1 cubic yard?

To mix 1 cubic yard of concrete, you typically need about 5 to 6 bags of Portland cement, depending on the specific mix design and the desired strength of the concrete. A standard 94-pound bag of Portland cement yields roughly 0.5 cubic feet when mixed. Therefore, for 1 cubic yard (27 cubic feet), approximately 5.7 bags would be required. Always check the specific mix requirements for your project, as variations can occur.


How many bags of pre-mix cement is needed to mix 1 cubic yds?

Cement comes in bags that weigh 94 lbs. The volume of the bag is approximately 1 cubic foot. If you want to mix concrete which is a mixture of a coarse aggregate (gravel) and a fine aggregate (sand) and something to bond the two aggregates together (cement) then firstly you need to know the strength concrete that you require. For 1 cubic yard of 3000psi (pounds per square inch) strength you will need about 6 bags cement 12 cubic feet of sand and 24 cubic feet of gravel. Rule of thumb is the ratio should be 1:2:4 (cement:sand:gravel)


How many bags do you need for 2 yards?

Bags of what? Grass seeds? Cement? Sugar?


How many 25kg bags of ballast and 25kg bags of cement are needed to make 1 cube meter of concrete?

To make 1 cubic meter of concrete, you typically need about 350 kg of cement and 700 kg of ballast (aggregates). Given that each bag of cement weighs 25 kg, you would need 14 bags of cement. For ballast, with each bag also weighing 25 kg, you would require approximately 28 bags of ballast.


How many 80 pound bags of cement for 1 cubic yard of 41 mortar mix?

You would need 31, 80 pound bags to cover 1 cubic yard at 4 inches deep. If you would like the depth to be 6 inches, 45 bags would be needed.