Baseline
A performance measurement baseline typically includes the cost baseline, schedule baseline, and scope baseline. The cost baseline details the project's budget, the schedule baseline outlines project milestones and deadlines, and the scope baseline defines the project's deliverables and requirements. These baselines serve as a reference for measuring and comparing actual project performance.
Schedule Scope Cost
The first step in developing a Performance Measurement Baseline is to define or scope all work involved.
schedule the work
1. Schedule 2. Cost 3. Scope
The Performance Measurement Baseline includes the project scope, schedule, and cost baseline. It sets the parameters for measuring and monitoring project performance against planned objectives. It is a key component of project management for tracking progress and ensuring project success.
the performance measurement baseline consists of
Functional Baseline: initial specifications established; contract, etc.Allocated Baseline: state of work products once requirements are approvedDevelopmental Baseline: state of work products amid developmentProduct Baseline: contains the releasable contents of the project
Product Baseline
No, an over target baseline is not a comprehensive rebaselining effort. It typically involves adjusting the project's performance measurement baseline to accommodate authorized changes in scope, schedule, or resources. It is not necessarily an internal re-planning effort but rather a realignment of the baseline to reflect changes.
The plan for completing the remaining contract effort is no longer achievable.
The plan for completing the remaining contract effort is no longer achievable.