answersLogoWhite

0

The average markup for Cost Plus contracts for Design Build vs EPC projects is about $ 1200.

User Avatar

Wiki User

10y ago

What else can I help you with?

Continue Learning about Civil Engineering

How many Types of contract in civil engineering?

Contract In law, a contract is a binding legal agreement that is enforceable in a court of law. That is to say, a contract is an exchange of promises for the breach of which the law will provide a remedy According to legal scholar Sir John William Salmond, a contract is "an agreement creating and defining the obligations between two or more parties". Construction contract Formal agreement for construction, alteration, or repair of buildings or structures (bridges, dams, facilities, roads, tanks, etc.). A construction contract is distinct from a contract to assemble, fabricate, or manufacture. While construction contracts serve as a means of pricing construction, they also structure the allocation of risk to the various parties involved. The owner has the sole power to decide what type of contract should be used for a specific facility to be constructed and to set forth the terms in a contractual agreement. It is important to understand the risks of the contractors associated with different types of construction contracts. Lump Sum Contract In a lump sum contract, the owner has essentially assigned all the risk to the contractor, who in turn can be expected to ask for a higher markup in order to take care of unforeseen contingencies. Beside the fixed lump sum price, other commitments are often made by the contractor in the form of submittals such as a specific schedule, the management reporting system or a quality control program. If the actual cost of the project is underestimated, the underestimated cost will reduce the contractor's profit by that amount. An overestimate has an opposite effect, but may reduce the chance of being a low bidder for the project. Unit Price Contract In a unit price contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has been removed from the contractor. However, some contractors may submit an "unbalanced bid" when it discovers large discrepancies between its estimates and the owner's estimates of these quantities. Depending on the confidence of the contractor on its own estimates and its propensity on risk, a contractor can slightly raise the unit prices on the underestimated tasks while lowering the unit prices on other tasks. If the contractor is correct in its assessment, it can increase its profit substantially since the payment is made on the actual quantities of tasks; and if the reverse is true, it can lose on this basis. Furthermore, the owner may disqualify a contractor if the bid appears to be heavily unbalanced. To the extent that an underestimate or overestimate is caused by changes in the quantities of work, neither error will effect the contractor's profit beyond the markup in the unit prices. Cost Plus Fixed Percentage Contract For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. Cost Plus Fixed Fee Contract Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. Cost Plus Variable Percentage Contract For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. Target Estimate Contract This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor's estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. Guaranteed Maximum Cost Contract When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation.


Related Questions

How is markup used to design a webpage?

Markup is used to design a webpage by listing its elements. Each element has a certain role in the creation of webpage.


Where do you use Hypertext markup language?

web design


What is the markup on golf irons?

The average markup for golf irons is about 40 to 50 percent. Higher end golf clubs will have a significantly higher markup.


What is the Formula for average markup?

2700+10%


What is the meaning of HTML?

HTML is stand for Hyper Text Markup language. HTML is a skeleton of your website. HTML is a markup language which is very useful for designing a website because without html we can't design a website that's why because html we provide all design pattern for design a website and all browser is only understand HTML format. For more info visit @javatpoint


What is mark up in web design?

A Markup or Markup language is the language like HTML or XHTML that websites are built with. It's the coding that separates a plain text document, that a computer would generally just read and display as text, into a Markup document. AXAT Technologies


What is the language used in the world wide web?

The language used to produce www pages is HyperText Markup Language or HTML.


Why is hyper text markup language a good language for the world wide web?

All the languages are "Good". But Hypertext Markup language is by far the easiest to learn.


What is the markup on brand name golf irons?

Depending on the brand, the markup on set of irons is between 40 and 300 percent. The average amount in is about 100 percent.


How do you design a website using HTML?

You can design a HTML page using proper markup tags. Applying tags at proper places can give you appropriate results.


What is a markup percent?

a markup percent


What's the full form of HTML?

HTML is stand for Hyper Text Markup language. HTML is a skeleton of your website. HTML is a markup language which is very useful for designing a website because without html we can't design a website that's why because html we provide all design pattern for design a website and all browser is only understand HTML format. For more info visit @javatpoint