NPV decreases when the cost of capital is increased.
The cost of capital is inversely proportional to the NPV. As capital costs increase (i.e. the interest rate increases), NPV decreases. As capital costs decrease (i.e. the interest rate decreases), NPV increases. You can see the relationship in the following equation: NPV = a * ((1+r)^y - 1)/(r * (1+r)^y) Where: NPV = Net Present Value (The present value of a future amount, before interest earnings/charges) a = Amount received per year y = Number of years r = Present rate of return
The NPV assumes cash flows are reinvested at the: A. real rate of return B. IRR C. cost of capital D. NPV
due to the uncertainty
If the opportunity cost of capital for a project exceeds the Project's IRR, then the project has a(n)
Yes, NPVs would change if the Weighted Average Cost of Capital (WACC) changed. A higher WACC would result in a lower NPV, while a lower WACC would result in a higher NPV. This is because the discount rate used in calculating NPV is based on the WACC.
NPV/Initial Cost of Investment
by considering npv analysis , irr and pay back period
on the basis of projects having higher npv
They explain the time value of money 􀂃 Both useful in capital budgeting and investment valuation
A change in the cost of capital will not, typically, impact on the IRR. IRR is measure of the annualised effective interest rate, or discount rate, required for the net present values of a stream of cash flows to equal zero. The IRR will not be affected by the cost of capital; instead you should compare the IRR to the cost of capital when making investment decisions. If the IRR is higher than the cost of capital the project/investment should be viable (i.e. should have a positive net present value - NPV). If the IRR is lower than the cost of capital it should not be undertaken. So, whilst a higher cost of capital will not change the IRR it will lead to fewer investment decisions being acceptable when using IRR as the method of assessing those investment decisions.
Equipment A NPV = 75000 - 120000 = 45000 Equipment B NPV = 50000 - 84000 = 34000 Based on NPV Equipment A should be selected
no it increases npv