Procedure:-
1) Let LOM is the horizontal angle to be measured as shown in fig. O is the station point
fixed on the ground by a peg. Set up the theodolite over the peg 'o' and level it
accurately.
2) Set the horizontal graduated circle vernier A to read zero or 360° by upper clamp
screw and slow motion screw. Clamp the telescope to bisect the bottom shoe of the
flag fixed at point 'L' and tighten the lower clamp. Exactly intersect the centre of the bottom shoe by means of lower slow motion screw. Check that the face of the
theodolite should be left and the telescope in normal position.
3) Check the reading of the vernier A to see that no slip has occurred .Also see that the
plate levels are in the centre of their run. Read the vernier B also.
4) Release the upper clamp screw and turn the theodolite clockwise. Biset the flag
bottom shoe fixed at point M by a telescope. Tighten the upper clamp screw and
bisect the shoe exactly by means of upper slow motion screw.
5) Note the reading on both the vernier to get the approximate value of the angle LOM.
6) Release the lower clamp screw and rotate the theodolite anticlockwise ai azimuth.
Bisect again the bottom shoe of the flag at 'L' and tighten the lower clamp screw. By
means of slow motion screw bisect exactly the centre of the shoe.
7) Release now the upper clamp screw and rotate the theodolite clockwise. Bisect the
bottom shoe of the flag fixed at M and tighten the upper clamp screw. By means of
slow motion screw bisect exactly the centre of the shoe. The vernier readings will bw
now twice the of the angles.
8) Repeat the process until the angle is repeated the required number of times (usually
3). Add 360° for every complete revaluation to the final reading and divided the total
angle by number of repetitions to get the value of angle LOM.
9) Change the face of the theodolite the telescope will now be inverted. Rrpeat the
whole process exactly in the above manner and obtain value of angle LOM.
10)The average horizontal angle is then obtained by taking the average of the
two angles obtained with face left and face right.
11)Usually three repetitions face left and three with face right should be taken and the
mean angle should be calculated.
by
M.laxminarayaan
In power house concreting during the installation of turbine units in their final location a second stage concrete is poured in order to embed the turbine units. A second stage concrete shall be non - shrinking,self compacting with quick setting admixtures for an early strength development
Yes, only use the first stage.
Biasing the transistor so that it remains into the linear range is one way the other way is to couple one stage to another via a capacitor to remove extra biasing DC voltage therefore remaining into the linear range
No simple answer to that. Usually, simple is good, but there's limit to how much pressure you can build with a single-stage pump. A two-stage pump will let you reach higher pressures, but is more complicated.
The power amplifier that drives the antenna. In CW transmitters and some AM transmitters this stage is also the modulator, in others (and in non-AM transmitters) the modulator is in an earlier stage.
EXIT Stage Left - 2008 Setting the Stage 1-9 was released on: USA: 25 April 2009
Tightening procedure: 1st stage: 22lbft 2nd stage: 43lbft 3rd stage: 65lbft 4th stage: loosen by 90degrees and retorque to 65lbft 5th stage: start and run the motor until fully warmed up and thermostat has opened, wait until totally cold 4 hrs later 6th stage: loosen by 90degrees and retorque to 65lbft
third
exposisiton
Competition for employees is often involved in setting the stage for compensation. Employees should be compensated for the amount of work they do as well as how well they do the job.
Snow White and the Huntsman Setting the Stage - 2012 was released on: USA: 5 April 2012
to describe the setting
backdrop
*find a theodolite or total station *check for collimation *check theodolite vertical axis *set up the theodolite a distance away from the foot of the tower, or closer but using a diagonal eye piece *use left face to bisect bottom point and clamp the horizontal plate *check the tower zenith transit and use the right face to bisect the bottom point and do as explained above *dont forget to record readings of every stage.
are a stage parent is a parent who hangs out backstage. Who helps with setting up ,etc etc
Tightening torques are: Stage 1 - 15Nm Stage 2 - 30Nm Stage 3 - 90Degrees
A. S. Gillette has written: 'Planning and equipping the educational theatre' -- subject(s): Stage-setting and scenery, Theater architecture, Theaters 'Stage scenery: its construction and rigging' -- subject(s): Stage-setting and scenery, Theaters