answersLogoWhite

0

A negative NPV (Net Present Value) project should generally not be accepted, as it indicates that the project's expected cash flows, discounted for risk and time, do not exceed the initial investment. Accepting such a project would lead to a decrease in the firm's value and shareholder wealth. It's essential to consider alternative investments that yield a positive NPV to maximize returns. However, in certain strategic situations, a negative NPV project might be considered if it aligns with long-term goals or market positioning.

User Avatar

AnswerBot

4mo ago

What else can I help you with?

Continue Learning about Finance

When the present value of the cash inflows exceeds the initial cost of a project then the project should be?

When the present value of the cash inflows exceeds the initial cost of a project, the project should be accepted. This indicates that the project is expected to generate a positive net present value (NPV), suggesting it will add value to the organization. Accepting such a project aligns with maximizing shareholder wealth and achieving financial growth.


When the net present value is negative the internal rate of return is the firm's cost of capital?

When the net present value (NPV) of a project is negative, it indicates that the project's expected cash flows, discounted at the firm's cost of capital, do not cover the initial investment. In this scenario, the internal rate of return (IRR) is indeed equal to the firm's cost of capital, meaning that the project is not generating sufficient returns to justify the investment. Therefore, the project would generally be considered unworthy of pursuit if the NPV is negative.


The net present value and profitability index methods to give consistent accept-reject decisions?

Yes, The PI and NPV always give the same decisions to accept or reject the projects. The Project's PI will be greater than 1.00 if the NPV is positive and PI will be less than 1.00 if the NPV is negative


Projects with a negative net present value should be?

Projects with a negative net present value (NPV) should generally be avoided, as they are expected to generate losses rather than profits over their lifespan. Investing in such projects can lead to a decrease in overall shareholder value. Instead, resources should be allocated to projects with a positive NPV, which are likely to enhance financial performance and contribute to the company's growth.


When Projects are mutually exclusive which project should be selected using npv and risk level?

Problems with project ranking: 1. Mutually exclusive projects of unequal size (the size disparity problem) - the NPVdecision may not agree with the IRR or PI. Solution: select the project with the larges NPV (not IRR). 2. The time disparity problem with mutually exclusive projects - NPV and PI assume cash flows are reinvested at the required rate of return for the project. IRR assumes cash flows are reinvested at the IRR. NPV decision may not agree with the IRR. Solution: select the project with the largest NPV. A good method to evaluate and rank project better is to use the Equivalent Annual Annuity (EAA) method. This is like calculating for PMT when doing TVM. It simply means, you will be getting that amount as an inflow each year or period. Therefore, you would want to choose the highest figure.

Related Questions

Why would a project have a negative NPV?

because, AMERICA!I'm a free man!


If the opportunity cost of capital for a project exceeds the projects IRR then the project has a NPV negative?

If the opportunity cost of capital for a project exceeds the Project's IRR, then the project has a(n)


When the present value of the cash inflows exceeds the initial cost of a project then the project should be?

When the present value of the cash inflows exceeds the initial cost of a project, the project should be accepted. This indicates that the project is expected to generate a positive net present value (NPV), suggesting it will add value to the organization. Accepting such a project aligns with maximizing shareholder wealth and achieving financial growth.


Harrys inc is considering a project that has the following cash flow and wacc data what is the projects npv?

Harry\'s Inc. is considering a project that has the following cash flow and WACC data. What is the project\'s NPV? Note that if a project\'s projected NPV is negative, it should be rejected. WACC: 14.75% Year 0 1 2 3 4 5 Cash flows -$1,000 $300 $300 $300 $300 $300 A. $10.58 B. $13.02 C. $11.63 D. $9.07 E. $10.12 You can also get answer on onlinesolutionproviders com thanks


When the net present value is negative the internal rate of return is the firm's cost of capital?

When the net present value (NPV) of a project is negative, it indicates that the project's expected cash flows, discounted at the firm's cost of capital, do not cover the initial investment. In this scenario, the internal rate of return (IRR) is indeed equal to the firm's cost of capital, meaning that the project is not generating sufficient returns to justify the investment. Therefore, the project would generally be considered unworthy of pursuit if the NPV is negative.


Why the NPV of a relatively long term project is more sensitive to changes in the cost of capital than is the NPV of a short term project?

due to the uncertainty


Should the Dixon Corporation buy the Collingsville plant?

Yes they should but only if they go ahead with the laminate technology investment. The value of the plant on its own is a negative NPV project based on a WACC of between 16-17%, which is where it should be. This is possibly why the price asked for the sale of Collinsville by ACC is 12 million. It could be argued that they have inclued some of the benefits of there R&D of the laminate into the asking price hence a negative NPV for the plant alone.


The net present value and profitability index methods to give consistent accept-reject decisions?

Yes, The PI and NPV always give the same decisions to accept or reject the projects. The Project's PI will be greater than 1.00 if the NPV is positive and PI will be less than 1.00 if the NPV is negative


For the NPV criteria a project is acceptable if the NPV is while for the profitability index a project is acceptable if the profitability index is?

less than zero, greater than the requred return


When a project npv exceeds zero?

When a project's Net Present Value (NPV) exceeds zero, it indicates that the projected earnings (in present value terms) from the project surpass the expected costs, also in present value terms. This suggests that the project is likely to generate value for the investors and is considered a good investment opportunity. A positive NPV implies that the project is expected to contribute to the overall wealth of the stakeholders. Consequently, it is generally recommended to proceed with projects that have an NPV greater than zero.


When reviewing the net present profile for a project?

When reviewing the net present value (NPV) profile for a project, it's essential to assess how changes in discount rates affect the project's NPV. A project is typically considered viable if its NPV is positive at the required rate of return. Additionally, the NPV profile can illustrate the project's sensitivity to different discount rates, helping decision-makers understand potential risks and returns. Evaluating the profile allows for informed comparisons with alternative projects or investments.


How does discount rate affect net present value?

The discount rate directly influences the net present value (NPV) by determining the present value of future cash flows. A higher discount rate reduces the present value of those cash flows, leading to a lower NPV, while a lower discount rate increases the present value and thus the NPV. If the discount rate exceeds the internal rate of return of a project, the NPV may become negative, indicating that the project may not be viable. Conversely, a lower discount rate can make an investment more attractive by increasing its NPV.