Change requests generated as a result of monitoring and control activities become an input the Perform Integrated Change Control Process

User Avatar

Wiki User

11y ago

What else can I help you with?

Continue Learning about Management

How is the close project or phase process linked to the direct and manage project work and perform integrated change control processes?

1) It uses accepented deliverables from the Validate SCope processes as inputs. 2) The project management plan, created or updated through the other processes, in an input to the close project or phase process


Which control related components should the manager include in the project management plan?

-How to perform configuration management -How to monitor and manage change -How to monitor and manage issues that arise


What is the need of project monitoring?

What is Monitoring & Controlling?In general, monitoring means watching the course, and controlling means taking action to either stay the course or change the wrong course. You monitor the project by generating, collecting, and distributing information about project performance against the baselines. Performance reports are used to monitor and control the project work. Deviations of performance results from the plan might indicate that some changes to the original project plan are required. Other change requests might come from stakeholders, such as expanding the project scope by adding new requirements. You control all these changes by influencing the factors that generate them, processing them through a system called the integrated change control system that contains a process called the Perform Integrated Change Control process, evaluating their impact across the project, and ensuring the implementation of the approved change requests.In addition to the schedule activities that need to be executed, the project management plan also contains a list of risks and the risk management plan. You monitor the risks by looking out for the risk triggers (the alerts that tell you a risk has occurred or is about to occur) for the already identified risks and by identifying new risks as the project progresses. You control the risks by executing the risk response plan and taking corrective and preventive actions. Quality is an integrated part of any project. Therefore, monitoring and controlling the project work includes controlling the quality. All these aspects of the project are monitored and controlled by using two high-level processes that belong to integration management: the Monitor and Control Project Work process and the Perform Integrated Change Control process. This also includes administering the procurement part of the project, which is another high-level process by its virtue.


What key principles of the perform integrated change control process should you follow?

-Project baselines should be changed only when necessary -Approved changes must be coordinated -The impact of change requests must be documented


What is the non-managerial employee?

It is the category of employees that perform tasks not involving the direction and control of enterprise activity.

Related Questions

How are the monitor and control project work and perform integrated change control process linked?

Change requests generated as a result of monitoring and control activities become an input the Perform Integrated Change Control Process


How is the close project or phase process linked to the direct and manage project work and perform integrated change control processes?

1) It uses accepented deliverables from the Validate SCope processes as inputs. 2) The project management plan, created or updated through the other processes, in an input to the close project or phase process


Which control related components should the manager include in the project management plan?

-How to perform configuration management -How to monitor and manage change -How to monitor and manage issues that arise


What is the need of project monitoring?

What is Monitoring & Controlling?In general, monitoring means watching the course, and controlling means taking action to either stay the course or change the wrong course. You monitor the project by generating, collecting, and distributing information about project performance against the baselines. Performance reports are used to monitor and control the project work. Deviations of performance results from the plan might indicate that some changes to the original project plan are required. Other change requests might come from stakeholders, such as expanding the project scope by adding new requirements. You control all these changes by influencing the factors that generate them, processing them through a system called the integrated change control system that contains a process called the Perform Integrated Change Control process, evaluating their impact across the project, and ensuring the implementation of the approved change requests.In addition to the schedule activities that need to be executed, the project management plan also contains a list of risks and the risk management plan. You monitor the risks by looking out for the risk triggers (the alerts that tell you a risk has occurred or is about to occur) for the already identified risks and by identifying new risks as the project progresses. You control the risks by executing the risk response plan and taking corrective and preventive actions. Quality is an integrated part of any project. Therefore, monitoring and controlling the project work includes controlling the quality. All these aspects of the project are monitored and controlled by using two high-level processes that belong to integration management: the Monitor and Control Project Work process and the Perform Integrated Change Control process. This also includes administering the procurement part of the project, which is another high-level process by its virtue.


What is the need of projection?

What is Monitoring & Controlling?In general, monitoring means watching the course, and controlling means taking action to either stay the course or change the wrong course. You monitor the project by generating, collecting, and distributing information about project performance against the baselines. Performance reports are used to monitor and control the project work. Deviations of performance results from the plan might indicate that some changes to the original project plan are required. Other change requests might come from stakeholders, such as expanding the project scope by adding new requirements. You control all these changes by influencing the factors that generate them, processing them through a system called the integrated change control system that contains a process called the Perform Integrated Change Control process, evaluating their impact across the project, and ensuring the implementation of the approved change requests.In addition to the schedule activities that need to be executed, the project management plan also contains a list of risks and the risk management plan. You monitor the risks by looking out for the risk triggers (the alerts that tell you a risk has occurred or is about to occur) for the already identified risks and by identifying new risks as the project progresses. You control the risks by executing the risk response plan and taking corrective and preventive actions. Quality is an integrated part of any project. Therefore, monitoring and controlling the project work includes controlling the quality. All these aspects of the project are monitored and controlled by using two high-level processes that belong to integration management: the Monitor and Control Project Work process and the Perform Integrated Change Control process. This also includes administering the procurement part of the project, which is another high-level process by its virtue.


An integrated router can perform the action of which other 2 devices?

switch and hub


What are the duties of piping supervisor?

The duties of a piping supervisor are to manage and instruct a team of workers to perform onsite installation processes. They also monitor job progress and ensure quality work is completed in a timely manner.


What can perform life processes independently?

an organism


Can a computer perform all our cognitive processes?

No


What are the cellular respiratory processes that lungs perform?

The lungs perform the following cellular respiratory processes - pulminory ventilation external respiration internal respiration


What are the inputs to the Perform Integrated change control process?

-A cost baseline from a previous similar project that's used to assess potential changes to the current project -A request to correct a scope overrun after a team member added functionality not required to a product, affecting time and schedule forecasts -A change control procedure for fast tracking and important change -A request that the widget cutting process is changed after quality control processes find a high number of widgets larger than specification


What examples are are inputs to the Perform Integrated Change Control Process?

-A cost baseline from a previous similar project that's used to assess potential changes to the current project -A request to correct a scope overrun after a team member added functionality not required to a product, affecting time and schedule forecasts -A change control procedure for fast tracking and important change -A request that the widget cutting process is changed after quality control processes find a high number of widgets larger than specification

Trending Questions
Why is activity definition the first process involved in project time management? What is the relationship between supply chain management and operation management? What are the different philosophies of management? How does the concept of agile vs adaptable apply to project management methodologies? According to Herzberg a sense of achievement earned recognition and interest in the work itself were? What is the best quality management training to apply for? How management affect Leadership social responsibility and ethics in government and Educational institutions? What is the difference between corporate governance and corporate social responsibility? What are some reasons that a managers most basic responsibility is to focus people on the activities to achieve desired outcomes? What is GMP training? Which element is not one of the position management considerations when determing what is needed for an organization to accomplish the mission? Horizontal integration differs from vertical integration in that it? What is a list of the components of logistics management? What is mean by principles of management? Project management is a continual balance between 3 main elements. What are they? What is the start-to-start dependency between Task A and Task B in the project schedule? Can there be more than one critical path in a given project schedule? Why is organisation important? What are the parts of the transactional process in their correct order? What is the difference between estimated cost and actual cost?