1.a) What is the need for metrics? What do you mean by indicators?
b) List the seven core metrics, their purpose and perspectives. [6+10]
2. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]
3.a) What are the five components of software cost models?
b) What are the components of a good cost estimate, in practice? [8+8]
4.a) Why does software didn't give as much returns on investment as other industries?
b) What are the ways of achieving better economics in Software? [8+8]
5.a) What are the primary objectives of the four phases of SW lifecycle?
b) What are the essential activities in Inception and elaboration phases? [8+8]
6.a) What are the seven workflows in the lifecycle?
b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]
7.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.
b) What are the benefits of matching people to roles? [10+6]
8.a) What are the sources of change? Why should change be made in a controlled way?
b) Define a configuration baseline. [10+6]
1.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.
b) What are the benefits of matching people to roles? [10+6]
2.a) What are the sources of change? Why should change be made in a controlled way?
b) Define a configuration baseline. [10+6]
3.a) What is the need for metrics? What do you mean by indicators?
b) List the seven core metrics, their purpose and perspectives. [6+10]
4. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]
5.a) What are the five components of software cost models?
b) What are the components of a good cost estimate, in practice? [8+8]
6.a) Why does software didn't give as much returns on investment as other industries?
b) What are the ways of achieving better economics in Software? [8+8]
7.a) What are the primary objectives of the four phases of SW lifecycle?
b) What are the essential activities in Inception and elaboration phases? [8+8]
8.a) What are the seven workflows in the lifecycle?
b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]
1.a) What are the primary objectives of the four phases of SW lifecycle?
b) What are the essential activities in Inception and elaboration phases? [8+8]
2.a) What are the seven workflows in the lifecycle?
b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]
3.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.
b) What are the benefits of matching people to roles? [10+6]
4.a) What are the sources of change? Why should change be made in a controlled way?
b) Define a configuration baseline. [10+6]
5.a) What is the need for metrics? What do you mean by indicators?
b) List the seven core metrics, their purpose and perspectives. [6+10]
6. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]
7.a) What are the five components of software cost models?
b) What are the components of a good cost estimate, in practice? [8+8]
8.a) Why does software didn't give as much returns on investment as other industries?
b) What are the ways of achieving better economics in Software? [8+8]
1.a) What are the five components of software cost models?
b) What are the components of a good cost estimate, in practice? [8+8]
2.a) Why does software didn't give as much returns on investment as other industries?
b) What are the ways of achieving better economics in Software? [8+8]
3.a) What are the primary objectives of the four phases of SW lifecycle?
b) What are the essential activities in Inception and elaboration phases? [8+8]
4.a) What are the seven workflows in the lifecycle?
b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]
5.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.
b) What are the benefits of matching people to roles? [10+6]
6.a) What are the sources of change? Why should change be made in a controlled way?
b) Define a configuration baseline. [10+6]
7.a) What is the need for metrics? What do you mean by indicators?
b) List the seven core metrics, their purpose and perspectives. [6+10]
8. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]
previous papers of ptsp with their answers
it is quite difficult to get UP previous exam paper but you can get other papers on website Aryanclasses.com, on this website almost all ntse previous papers are available.
where can you get previous year question papers of tgt socieal science of dsssb
i need commerce question papers
i want 2011 engineering previous question papers
u can get the question papers in the management library of School of management studies in jntu campus
software engineering
Open office provides decent quality programs for free. the next best to Microsoft office programs. openoffice allows for power points, papers, flow charts, etc.
june 2012 , november 2012 and june 2013
i want organizational communication previous papers regular
yes
previous papers of ptsp with their answers
Einstein Papers Project was created in 1986.
WANTED PREVIOUS SEMESTER VTU QUESTION PAPERS ON E.V.S
yes i want previous papers for 3rd sem
i want previous vlsi question papers
yes i want previous questtion papers