1.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

2. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

3.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

4.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

5.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

6.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

7.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

8.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

1.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

2.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

3.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

4. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

5.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

6.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

7.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

8.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

1.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

2.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

3.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

4.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

5.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

6. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

7.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

8.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

1.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

2.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

3.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

4.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

5.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

6.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

7.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

8. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

User Avatar

Wiki User

12y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: Jntu previous papers of software project management?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Can i get previous years question papers of MBA first year second semester?

u can get the question papers in the management library of School of management studies in jntu campus


Show previous uptu question papers of MCA 5th semester?

software engineering


Where can I get free project management software?

Open office provides decent quality programs for free. the next best to Microsoft office programs. openoffice allows for power points, papers, flow charts, etc.


Personnel management question papers for previous exams?

june 2012 , november 2012 and june 2013


Jntu kakinada MBA 1st year organisational communication and data base management system question papers?

i want organizational communication previous papers regular


Previous question papers of MCom Final Year Financial Management of School of Distance Education Andhra University?

yes


Solved previous papers of PTSP with their answers?

previous papers of ptsp with their answers


When was Einstein Papers Project created?

Einstein Papers Project was created in 1986.


Tancet model papers previous papers help your mail id is kiranbugudegmailcom?

WANTED PREVIOUS SEMESTER VTU QUESTION PAPERS ON E.V.S


You want see previous papers of MBA of uptu?

yes i want previous papers for 3rd sem


Jntu vlsi design btech previous question papers?

i want previous vlsi question papers


You want previous question papers of engineering mathematics ma1x01?

yes i want previous questtion papers