answersLogoWhite

0

1.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

2. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

3.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

4.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

5.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

6.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

7.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

8.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

1.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

2.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

3.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

4. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

5.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

6.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

7.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

8.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

1.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

2.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

3.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

4.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

5.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

6. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

7.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

8.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

1.a) What are the five components of software cost models?

b) What are the components of a good cost estimate, in practice? [8+8]

2.a) Why does software didn't give as much returns on investment as other industries?

b) What are the ways of achieving better economics in Software? [8+8]

3.a) What are the primary objectives of the four phases of SW lifecycle?

b) What are the essential activities in Inception and elaboration phases? [8+8]

4.a) What are the seven workflows in the lifecycle?

b) What levels of activity take place in these workflows during each of the four phases (Inception, elaboration, construction and transition)? [8+8]

5.a) What are the steps in identifying project roles? Name any five project roles and the skills needed for them.

b) What are the benefits of matching people to roles? [10+6]

6.a) What are the sources of change? Why should change be made in a controlled way?

b) Define a configuration baseline. [10+6]

7.a) What is the need for metrics? What do you mean by indicators?

b) List the seven core metrics, their purpose and perspectives. [6+10]

8. What were the metrics collected in CCPDS-R? What is the purpose of each metric? [16]

User Avatar