answersLogoWhite

0

Any individual who has worked in the software industry for at least 2 years will invariably agree with the fact that, we all slog. Most of our estimates miss the target by quite a bit and the whole team slogs like crazy during the last 2-3 months of the project and finish the delivery. The cause could be scope increase, attrition, or because of any numerous other possibilities. But, almost always, the reason is bad estimates. The team that estimated this work, underestimated the complexity and allotted much less time that what would be required to finish this. So, the eventual result is, the team members slog their backsides off to finish the project.

If I were project manager, I will do everything in my power to ensure that my guys don't have to slog it out in the end…

User Avatar

Wiki User

12y ago

What else can I help you with?

Related Questions

How do the nervous system and the endocrine system differ in their control of body activities?

Speed and duration. Nerves are faster, hormones last longer.


What are the main activity types in Primavera P6?

In Primavera P6, the main activity types are: Task Dependent Duration is calculated based on relationships and calendar. Most commonly used for normal project activities. Resource Dependent Duration is driven by assigned resources and their calendars. Used when work duration depends on manpower or equipment. Level of Effort (LOE) Has no fixed duration; it spans between two activities. Used for support work like supervision or project management. Start Milestone Represents an important start event with zero duration. Finish Milestone Represents an important completion event with zero duration. These activity types help control how schedules are calculated and managed in Primavera P6


What is the duration of Beyond Our Control?

The duration of Beyond Our Control is 1800.0 seconds.


What is the duration of The Limits of Control?

The duration of The Limits of Control is 1.93 hours.


What is the duration of Losing Control?

The duration of Losing Control is 1.52 hours.


What is the duration of Control TV?

The duration of Control TV is 240.0 seconds.


What is the duration of Rent Control film?

The duration of Rent Control - film - is 1.58 hours.


What is the duration of Birth Control Revolution?

The duration of Birth Control Revolution is 1.27 hours.


What is the duration of Out of Control TV series?

The duration of Out of Control - TV series - is 1440.0 seconds.


What are activities in Primavera P6?

Activities in Primavera P6 are the individual tasks or work elements that must be performed to complete a project. They are the building blocks of the project schedule, and each activity represents a specific piece of work with a defined duration, start, and finish. Key points about activities in Primavera P6: Each activity has a start date, finish date, and duration Activities are linked to each other using relationships (FS, SS, FF, SF) Resources (labor, material, cost) can be assigned to activities Activities help determine the critical path of the project Progress is tracked by updating actual dates, remaining duration, or percent complete Types of activities in Primavera P6: Task Dependent – duration is driven by activity logic Resource Dependent – duration depends on assigned resources Level of Effort (LOE) – measures work based on other activities WBS Summary – summarizes activities under a WBS Milestone – represents key events (start or finish) Why activities are important: Activities allow planners and project managers to: Plan and sequence work accurately Monitor progress and delays Control time and cost Analyze schedule performance


What is the duration of Remote Control game show?

The duration of Remote Control - game show - is 1800.0 seconds.


Why is a controlled group important?

A control group is important so you can tell if the thing you are testing changes whatever you are testing it on in any way.