Want this question answered?
Organizational process assets Scope management plan The project charter Requirements documentation
The Project Charter, Req Documents, Scope management Plan, Organizatioanl Process assets
Yes. The Scope Baseline - which is part of the overall Project Management Plan is used as an input to the Verify Scope process
The Project Management Plan tells you how to manage all of the different knowledge areas, and it has baselines for the scope, schedule and budget. The Scope Management Plan is one of the subsidiary plans inside the project management plan. It has really specific procedures for managing scope. For example, it tells us which stakeholders we need to talk to when gathering requirements. It lists what tools and techniques we are planning to use when we use the Scope Definition to define the scope. And when there's an inevitable change because even the best project manager can't prevent every change, it gives him procedures for doing Scope Management. So even though the Scope Management Plan is created in the Develop Project Management Plan process, it's used throughout all of the Scope Management processes.
The project's scope management plan will define how scope changes will be addressed and controlled throughout the project. The requirements management plan will outline how project requirements will be identified, documented, and managed, including how changes to requirements will be addressed.
The control process in project management involves monitoring project performance, comparing it to planned objectives, and taking corrective action to ensure project success. It includes tracking progress, identifying deviations from the plan, and implementing adjustments to keep the project on track and within scope.
scope management
A Projects Scope outlines what work will be done/accomplished as part of the project and also outlines what would not be done as part of the current project Without a list of what needs to be done, how can you expect a team to execute a project? Without knowing what to do, the team will be lost and eventually the project will be a failure. The project scope is created in the "Define Scope" process and how the project scope is handled is outlined in the Scope Management Plan
Scope creep refers to scope changes applied without processing them though the change control process. The role of the Project Manager is to ensure that Scope Creep does not happen in their project. As per the PMBoK guide, the Control Scope process is used to control the projects scope.
Project scope statement Requirements documentation Enterprise environmental factors Scope management plan Organizational process assets
scope of bank cash management
To perform the Define Activities process in project management, you typically need the project scope statement, work breakdown structure (WBS), project schedule constraints, and any relevant historical data or lessons learned from similar projects.