Explain the Different Activity Types Available in Primavera P6

Primavera P6 provides several activity types to represent different kinds of work and milestones within a project schedule.

  1. Task Dependent Activity

The most commonly used activity type.

Its duration and dates are controlled by the activity's relationships and assigned calendar.

Used for normal project tasks such as excavation, concreting, installation, and testing.

Example: Concrete pouring for a foundation.

  1. Resource Dependent Activity

The activity schedule is driven by the calendars of the assigned resources rather than the activity calendar.

Useful when resource availability determines when work can be performed.

Example: Specialized equipment installation that depends on the availability of a certified technician.

  1. Level of Effort (LOE)

Represents ongoing support activities that occur over a period of time.

Duration is automatically calculated based on the activities it supports.

Does not usually affect the project's critical path.

Example: Project management, supervision, quality control, and site administration.

  1. Start Milestone

Represents a significant event marking the beginning of a phase or project.

Has zero duration.

Used to indicate important start points.

Example: Notice to Proceed (NTP) received.

  1. Finish Milestone

Represents a significant event marking the completion of a phase or project.

Has zero duration.

Used to indicate important completion points.

Example: Project Handover Completed.

  1. WBS Summary Activity

Summarizes all activities within a specific WBS element.

Duration and dates are automatically calculated from the activities under that WBS.

Primarily used for reporting and monitoring.

Example: A "Civil Works" summary activity showing the overall duration of all civil construction activities.

User Avatar

Himanshi kaur

Lvl 8
1mo ago

What else can I help you with?

Related Questions

What is Lag and Lead in Primavera?

What is Lag and Lead in Primavera P6? Lag and Lead are used in Primavera P6 to control the time gap between two activities in a schedule relationship. Lag Lag is a delay between two activities. It adds extra waiting time after the predecessor activity before the successor activity can start or finish. Lag is usually written as + days. Example: Activity A → Activity B (Finish-to-Start +3 days) Activity A finishes on Day 5 Activity B will start on Day 8 Because there is 3 days lag (waiting time) Simple Meaning: Lag = Waiting time between activities Lead Lead is the overlapping time between two activities. It allows the successor activity to start before the predecessor activity finishes. Lead is shown as a negative lag (-) in Primavera. Example: Activity A → Activity B (Finish-to-Start -2 days) Activity B starts 2 days before Activity A finishes. Simple Meaning: Lead = Activities overlap Short Definition Lag: Delay between activities (+ time) Lead: Overlap between activities (- time) If you want, I can also explain with a simple construction example used in Primavera planning (like concrete, curing, plaster work).


Explain with example how charts are used in analysis Also explain the different types of charts available in Excel?

"http://wiki.answers.com/Q/Explain_with_example_how_charts_are_used_in_analysis_Also_explain_the_different_types_of_charts_available_in_Excel"


How do you explain the olympic games to little children?

It is an activity where people from different countries come together to compete in different competitions and races to win glory for their country


How do you report illegal activity in family court in South Carolina?

explain activity


Explain the scope of different types of assurance engagement?

Which types of scopes are available that enable us to manage IP addresses?


How does evolution explain the existence of paranormal activity?

It does not. Paranormal activity is not supported by any evidence I am aware of.


What does BAS stand for and explain its use?

business activity statement


How much different types of well known computer processor available in market briefly explain?

There are only 2, AMD and Intel. Intel is better in my opion.


Do you have some great activities that help students learn the different genres of literature?

You can hold an activity where there are different centers. In each center would be a different type of genre. Next, have a narrative at each center. From their, students have to explain why it is that type of genre and what that type of genre pertains to.


How do you explain the different ways in which the Indian peoples of Mesoamerican and North America developed?

The difference in the civilizations of ancient America developed into two different ideologies of government; this is mainly due to the geography of the land, and the supplies that were available.


Explain with help of an an example how FAT different from inode?

explain with help of an example, how FAT is different from inode.


Explain characteristics of different types of organsational structures in management function and behavior?

Explain different types of ability