answersLogoWhite

0


Best Answer

Construction in Progress (C-in-P) is an inventory account and Progress Billings is a contra account that relates to it. When a contractor incurrs costs from the process of construction it debits it to C-in-P. Here's an example transaction is as follows: C-in-P 10,000

Cash, A/P, etc. 10,000 Depending on whether the contractor is accounting via the completed contract method or percentage of completion method determines the ultimate balance of C-in-P. If percentage of completion method is used then the Gross Profit that results from the yearly recognition of revenue is debited to C-in-P as a sort of value added until the contract's completion. Progress Billings is credited every time an invoice is sent to the customer in request for funds. An example transation is as follows: A/R 15,000

Progress Billings 15,000 At the end of the contract Progress Billings should equal the amount to be collected from the customer. C-in-P and Progress Billings will appear on the Balance Sheet as follows: C-in-P 30,000

Progress Billings <25,000>

Progress in Excess of Billings 5,000 If the current balance of C-in-P is larger than the current balance in Progress Billings it will appear as an asset. If reversed it will appear as a liability because the customer will have greaty equity in the project than the contractor.

User Avatar

Wiki User

16y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: How are the balances of progress billings and construction in progress shown at reporting dates prior to the completion for a long term contract?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What is billings on construction in process?

It's a contra-asset account to construction in process. It's used to record periodic billings on a construction project.


What is Billings in excess of costs?

I am not an accountant; but I work with Billings in excess of costs. Billings in excess of cost is a product of estimating allocated cost and direct cost of a construction contract. This is used in Percentage of Completion basis of financial statement preperation. Billings in excess is liability; Cost in excess of Billings is an asset. An example: Total Contract: $1,000,000. Estimated Cost is $900,000; Estimated Profit is $100,000. You start working the job, at year end you have the following Contract $1,000,000; Total Estimated cost: $900,000; Actual Cost to Date: $450,000; Billings to Date are $600,000; so: 450/900=50% X $1,000,000= $500,000 Earned to date; $500,000 Earned to date - $600,000 Billings to date = $100,000 Billings in Excess of Cost. If you only had $400,000 in Billings to date it would be: $500,000 - $400,000= $100,000 Cost is excess of Billling . Actual Cost to Date / Estimated Cost X Contract Amount = Earned to Date - Billed to Date = (if negative number = Billings in Excess of Costs) (if positive number = Cost in Excess of Billings) Billings in Excess of Costs is a balance sheet liability Cost in Excess of Billings is a balance sheet asset


Differences between completed contract method and the percentage of completion method?

In the construction industry, two accounting approaches have developed over the years regarding the recognition of revenue. The first approach-the completed-contract method-does not recognize any profit until the construction project is complete. The second approach-the percentage-of-completion method-recognizes profit on a piecemeal basis.The logic behind the percentage-of-completion method is that both the buyer and seller have obtained enforceable rights. The buyer has the right to require specific performance on the contract; the seller has the right to require progress payments. Thus the facts seem to indicate that a continuous "sale" is in progress.According to Statement of Position 81-1, the percentage method should be used if estimates of progress toward completion, revenues, and costs are reasonably dependable, and all the following conditions exist:The contract clearly specifies the rights regarding goods or services to be provided, and the consideration to be exchanged.The buyer can be expected to satisfy all the contractual obligations.The contractor can be expected to perform the contractual obligations.If these conditions have not been met, then the completed-contract method should be used. It should be emphasized that the total profit on the construction project is the same under both methods.The difference between methods is simply a question of timing-the percentage method recognizes profit little by little over time, while the completed-contract method defers the entire profit until completion.Let's go in detail with case examples, its formula, calculation and journal entries&acirc;&euro;&brvbar;&acirc;&euro;&brvbar;The Completed-ContractThis method defers all the profit on the construction project until the completion date. During the construction period, all costs incurred are debited to an inventory account called"Construction in Process". This is similar to the Work in Process account used in cost accounting. Billings are debited to Accounts Receivable and credited to an account called"Billings on Construction". This is not a revenue account since this method does not recognize any revenue or profit until completion. Rather, it is a contra asset to the Construction in Process Account. Finally, at completion, the construction and billings accounts are closed, and the difference between them is recognized as gross profit.For easier understanding, let's construct some examples&acirc;&euro;&brvbar;..Example-1Construction Corporation enters into a contract on January 1, 19A, with the Department of City Development to build a small building for $100,000. The project is estimated to take 3 years. The following information presents the transactions that took place over this time:Notice that the final profit is $30,000 ($100,000 ? $70,000). Also notice that the estimate of what the final profit would be changed between 19A and 19B. In 19A it was $35,000 (selling price of $100,000 ? $20,000 of costs incurred so far ? $45,000 of estimated completion costs). In 19B it changed to $30,000 ($100,000 ? $20,000 ? $25,000 ? $25,000). The journal entries for the three years would be as follows:By the end of 19C, the "billings account" and the "Construction in Process account" appear as follows:The journal entry in 19C (to close these accounts and recognize profit) would be:[Debit]. Billings on Construction = $100,000[Credit]. Construction in Process = $70,000[Credit]. Income on Construction = $30,000The information given regarding estimated completion costs was not needed in this problem. However, it is relevant if the percentage-of-completion method is used instead of the completed-contract method.Notes: The account Billings on Construction is a contra to the construction account and is shown on the balance sheet as such. If its balance is less than the balance in the construction account, the net amount is shown as a current asset; if it is more, the net amount is shown as a current liability.Example-2In the previous example, the balance sheets for 19A and 19B would appear as follows:Note: The income statements for 19A and 19B would not show any revenue or profit since these items are deferred until completion.Example-3If in 19X1 Corporation X has construction costs of $50,000 and billings of $38,000, its balance sheet would show:The Percentage-Of-Completion MethodThis method recognizes a portion of the gross profit each year based upon the following formula:Recognized rofit:The entries each year would be the same as under the completed-contract method, with one additional annual entry to recognize profit. This entry debits the construction account (the profit is placed "into" the inventory) and credits a profit account.Example:Let's use the same information as in Example-1. The journal entry in 19A for profit recognition is:[Debit]. Construction in Process = $10,769[Credit]. Income from Construction = $10,769The calculation is:At this point, the expected profit is $35,000 (selling price of $100,000 - past costs of $20,000 - future costs of $45,000).The $10,769 would be shown on the 19A income statement. In 19B the profit recognized is:Notice that the total expected profit has changed from $35,000 to $30,000 due to changes in anticipated costs. This happens often in the construction industry.The $30,000 total expected profit is computed as follows:The 19B income statement would show profit of $8,517 and the journal entry would be:[Debit]. Construction in Process = $8,517[Credit]. Income from Construction = $8,517While in 19C:A journal entry would be made for this amount. An examination of the accounts at the end of 19C reveals the following:Notice that the balances of these two accounts are equal (at $100,000) under this method. This is because the construction account contains both cost and profit.One final journal entry would be made at the end of 19C to close these two accounts:[Debit]. Billings on Construction = $100,000[Credit]. Construction in Process = $100,000Note: If at any time during the construction period it is estimated that a loss will occur on the project (because the estimated total costs are expected to be higher than the selling price), it should be recognized by a debit to a loss account and a credit to the inventory account. Furthermore, if in previous years profit was recognized under the percentage-of completion method, it should now be nullified via a reversing entry.Next Example:A company used the completed-contract method for a 5-year construction project. Thus no profit would be recognized until the fifth year. During the third year the company realizes that the total project will result in a net loss of $50,000. The company should immediately make the following journal entry:[Debit]. Loss on Construction = $50,000[Credit]. Construction in Process = $50,000One Final Example:In the previous example, assume the company used the percentage-of-completion method and recognized profit of $10,000 and $20,000, respectively, in the first 2 years. In the third year, upon discovery of the $50,000 loss, an entry must be made to both recognize this loss, and to nullify the previous profit. The journal entry would be:[Debit]. Loss on Construction = $80,000 *[Credit]. Construction in Process = $80,000Note: *10,000 + 20,000 + 50,000Source: http://accounting-financial-tax.com/2008/09/revenue-recognition-completed-contract-and-percentage-of-completion-method/


Where is the Parmly Billings Library in Billings located?

The address of the Parmly Billings Library is: 510 North Broadway, Billings, 59101 1196


Where is the Billings Depot in Billings Montana located?

The address of the Billings Depot is: 2310 Montana Ave, Billings, MT 59101-2420


What is the birth name of Eric Billings?

Eric Billings's birth name is Billings, Eric Scott.


What is the birth name of Jeff Billings?

Jeff Billings's birth name is Jeffrey David Billings.


What is the birth name of Brandon Billings?

Brandon Billings's birth name is Brandon James Billings.


Where is the Parmly Billings Library Bookmobile in Billings located?

The address of the Parmly Billings Library Bookmobile is: 510 North Broadway, Billings, 59101 1196


i need a listing of sold houses in billings,mt?

These are some of the building currently sold by the owner in Billings, MT.1239 Lewis Ave, Billings MT. 4293 Smohawk Trl, Billings MT. 122 Charlene St, Billings MT. 740 Constitution Ave, Billings MT. 724 Avenue F, Billings MT. 225 Jackson St, Billings MT


Where is the Billings Baseball Preservation Society in Billings Montana located?

The address of the Billings Baseball Preservation Society is: 1735 Mariposa Lane, Billings, MT 59102-2419


Which airport is near Billings MT?

Billings Logan International Airport - Billings, MT (BIL / KBIL).