35 to 70
It depends on the mix of concrete you are using. A basic 1-2-3 mix is 5 1/2 cubic feet of portland cement (a wheelbarrow, depending on its size, holds 1/2 to 1 cubic feet), 11 cubic feet of sand, and 16 1/2 cubic feet of stone (called aggregate) from 1/2 to 1 inch in size each. To this is added about 12-15 gallons of water.(1 1/2 to 2 cu.ft.). This will make just a little less than 1 cubic meter of concrete.
A weaker mix for basic work not needing structural strength a 1-2-3 mix of 1 part stone, 2 parts cement and 3 parts sand can be used, this would require a bit less than 1 part water.
A stronger mix of 1 part cement, 1 1/2 parts sand and 3 parts stone with about 1/2 part water is good for heavy duty concrete work. Stone will increase the strength of concrete and sand will weaken it. Using too much or too little water in the mix will weaken it as well. Additionally, concrete with too much water or too little cement tends to shrink and crack as it sets. The amount of water to use is mainly dependent on the cement in the mix. There should be at least half as much cement as sand in any mixture. The amount of stone to use should be between 1/4 and 3/4 of the total mixture. Grouts and mortars use no stone and may add limestone as an additional binder. These should not be used for structural concrete, but can be used for foundation pointing, bolt anchoring or mortaring brickwork.
cubic feet per minute
The weight of unfilled polycarbonate is 0.0433297 pounds per cubic inch
Cubic Meters Per Hour:A measurement of airflow that indicates how many cubic meters of air pass by a stationary point in one hour. Cubic meters per hour is abbreviated m³/hr.
Short for cubic feet per minute, a measurement of the velocity at which air flows into or out of a space.
cfm stands for cubic feet per minute - this is a term that describes the amount of air flow in duct work - it takes approximately 400 cubic feet per minute air flow per ton of air conditioning
4000PSI, 12bags, .5cum3sand 1cu.m3 gravel
500 pounds cement, 1500 pounds sand, 1600 pounds gravel. Mix with 32 gallons water
The number of wheelbarrows of aggregate in 1 cubic metre of concrete depends on the size of the wheelbarrow and the aggregate's density. Typically, a standard wheelbarrow holds about 0.1 cubic metres of material. Therefore, you would need approximately 10 wheelbarrows of aggregate to fill 1 cubic metre of concrete, assuming the wheelbarrow is filled to capacity.
That depends on what size the concrete truck is. A 10-yard truck carries about 270 cubic feet when full. An 8 cubic yard truck carries about 216 cubic feet of concrete. (Or gravel, sand, etc)
One cubic meter of concrete is equal to 1.308 cubic yards of concrete. If there are 5 1/2 bags of cement in 1 cubic yard of concrete, there would be 7.2 bags in 1 cubic meter of concrete. These are the 94 pound bags of portland cement or roughly 40kg bags so figure 8 bags total. Some will be left over
To make one cubic yard of concrete, you typically need about 1 part Portland cement, 2 parts sand, and 3 parts gravel. This translates roughly to 1 bag (94 lbs) of Portland cement, 0.5 cubic yards of sand, and 0.75 cubic yards of gravel. Adjustments may be needed based on the specific mix design and desired strength. Always consult local guidelines or concrete calculators for precise measurements.
To cast 41 cubic yards of concrete, you typically use a mix ratio of 1 part cement, 2 parts sand, and 3 parts gravel (aggregate). For 41 yards of concrete, you'll need approximately 6.8 cubic yards of cement, 13.6 cubic yards of sand, and 20.4 cubic yards of gravel. Adjust the mix based on specific project requirements or concrete strength needed. Always consider adding water based on the moisture content of the materials and desired workability.
Concrete is a mixture of sand, gravel, cement, and water. Generally, you have 1 part cement, 2 parts sand, and 3 parts gravel. Sand makes up about 1/4 or 1/3 of a cubic foot. At 100 pounds per cu ft that is about 25-35 pounds.
To make one cubic yard of concrete, you typically need about 1.5 tons (or 3,000 pounds) of sand and gravel combined. The standard mix for concrete is roughly 1 part cement, 2 parts sand, and 3 parts gravel, along with water. This means you would generally use about 0.5 cubic yards of sand and 0.75 cubic yards of gravel for each cubic yard of concrete. Adjustments may vary based on the specific mix design and desired strength.
First, things are not made of cement- they are made of concrete- which consists of cement, sand, gravel and water. Mix them using 1 part cement, 1.5 parts sand, 3 parts gravel. To calculate how much CONCRETE you need, multiply depth X width X length in inches, then divide by 1728. This will tell you the number of cubic FEET of concrete. To get the number of cubic YARDS, divide the cubic feet by 27. If you are using packaged concrete mix (Sakrete is one) then an 80 lb bag makes 0.6 cubic feet of concrete. NOTE: If you are working with concrete for the first time- do not add too much water (weakens the concrete) and do not get wet concrete on bare skin- it will cause a chemical burn. Wash it off promptly if you do.
The number of wheelbarrows in a ton of gravel can vary based on the size of the wheelbarrow and the density of the gravel. A standard wheelbarrow typically holds about 6 cubic feet, and a ton of gravel is approximately 20 cubic feet. Therefore, you would need about 3 to 4 wheelbarrows to transport a ton of gravel, depending on how full each wheelbarrow is loaded.
The mixture depends on the concrete strength, flow properties and other specifications required, quality of cement, aggregates and other chemical additives that will be used. Typically 1 cubic meter concrete should include about 310kg cement, 800kg sand, 900kg gravel and 220kg water.