answersLogoWhite

0


Want this question answered?

Be notified when an answer is posted

Add your answer:

Earn +20 pts
Q: What Item rate or BOQ Contract?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What is an Item-Rate Contracts Or Percentage Rate Contracts?

In item rate contracts means each and every work of the building having an separate rate. for example construction of a building earth work having separate rate PCC having Separate rate, RCC Having Separate rate


What is schedule of rate contract?

A schedule of rates can be the Bill of Quantities (BOQ), where, based on the design issued by or on behalf of the Employer/Contracting Authority, a list with the items will be included, together with their rates. The items will be used when measuring and valuating the works done by the contractor for payment purpose. The BOQ consist of a list with these items described above, the quantity of each item, as estimated by or on behalf of the Employer/Contracting Authority, and the rates included by each bidder at the bidding time. The quantities and the rates allows the bidder to calculate his bid value and the Employer/Contracting Authority to award the contract based (also) on the value of the bid. The BOQ is used in construction contracts where there is a design issued by or on behalf of the Employer/Contractor Authority, which allow the estimation the quantity for each item of work. This will allow the payment of the actual work done by the contractor, at the rates included by the contractor in the BOQ, at the bidding time, and the lowest contract price possible, because the risk of the contractor is the lowest as regards the total cost of the contract. Another kind of contract can be the lump sum contract, when, because the actual quantities of works cannot be estimated due to the lack of the (detailed) design at the bidding time. Sometimes only a preliminary design or even only Employer's specifications exist at the bidding time, and the bidders are to estimate the final cost of the works, and to state which their bid value is. In order to cover the high degree of uncertainty when (detailed) design is not available, the bidders will declare higher contract values, and, therefore, the contract will be awarded with higher accepted contract price. by-sin


What is schedule of rate?

A schedule of rates can be the Bill of Quantities (BOQ), where, based on the design issued by or on behalf of the Employer/Contracting Authority, a list with the items will be included, together with their rates. The items will be used when measuring and valuating the works done by the contractor for payment purpose. The BOQ consist of a list with these items described above, the quantity of each item, as estimated by or on behalf of the Employer/Contracting Authority, and the rates included by each bidder at the bidding time. The quantities and the rates allows the bidder to calculate his bid value and the Employer/Contracting Authority to award the contract based (also) on the value of the bid. The BOQ is used in construction contracts where there is a design issued by or on behalf of the Employer/Contractor Authority, which allow the estimation the quantity for each item of work. This will allow the payment of the actual work done by the contractor, at the rates included by the contractor in the BOQ, at the bidding time, and the lowest contract price possible, because the risk of the contractor is the lowest as regards the total cost of the contract. Another kind of contract can be the lump sum contract, when, because the actual quantities of works cannot be estimated due to the lack of the (detailed) design at the bidding time. Sometimes only a preliminary design or even only Employer's specifications exist at the bidding time, and the bidders are to estimate the final cost of the works, and to state which their bid value is. In order to cover the high degree of uncertainty when (detailed) design is not available, the bidders will declare higher contract values, and, therefore, the contract will be awarded with higher accepted contract price. by-sin


When was Boq created?

Boq was created in 1900.


Who is Loq in OZ?

I assume you meant Boq. In the book The Wonderful Wizard of Oz, Boq is a rich Munchkin Dorothy spends the night with before she begins her journey. In the book Wicked, Boq is a friend of Elphaba, the Wicked Witch of the West. In the play Wicked, Boq becomes the Tinman.


What is the purpose of BOQ?

BOQ aims to give builders an estimation of cost to construct a residential building or a commercial building.


Who played Boq in 'Wicked' in the United States in 2007?

The following actors played Boq in performances of 'Wicked' in the United States of America in 2007:1. On Broadway, Logan Lipton was Boq.2. On the first national tour, Josh Lamon was Boq until Brad Weinstock took over on June 6.3. In Chicago, Adam Fleming was Boq until Stanton Nash took over on May 8.4. In Los Angeles, Adam Wylie [b. May 23, 1984] was Boq.


What is sodium hypochlorite made out of?

boq


What is preliminaries in BOQ?

road preliminaries?


What are some unique facts about France?

boq


What does boq stand for?

It stands for Bill Of Quantities


What is a BOQ barrack?

That is where unmarried officers can live.