answersLogoWhite

0


Best Answer

Successor is the number that comes just after a particular number is called its successor.

Ex: Successor of 823 is 824 , Successor of 3424 is 3425

Predecessor is the number that comes just before a particular number is called its predecessor.

Ex: 999 is the predecessor of 1000, 2367 is the predecessor of 2368

Some more Example on Successor are

  • Successor of 589 is 590
  • 3724 is 3725
  • 5099 is 5100
  • 7009 is 7010
  • 4836 is 4837
  • 6149 is 6150

Some more examples on predecessor are

  • 495 is predecessor of 496
  • 999 is predecessor of 1000
  • 7054 is predecessor of 7055
  • 6825 is predecessor of 6826
  • 3209 is predecessor of 3210
  • 9998 is predecessor of 9999
User Avatar

Wiki User

11y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is the difference between predecessor and successor when drawing activity on arrow in it project management?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

How do you determine the timing of activities?

The activity sequencing process is used to arrange the schedule activities in the appropriate order, which takes into account the dependencies among the activities. For example, if Activity B depends upon the product of Activity A, then Activity A must be performed before Activity B.By definition, the successor activity must start after the predecessor activity has already started. But exactly when can the successor activity start after the predecessor activity has already been started?Well, both the predecessor and the successor have a start and a finish, and there are at maximum four possible combinations between the start and finish points of the predecessor and the successor activities. Accordingly, there are four kinds of dependencies, also called precedence relationships or logical relationships, listed here:• Finish to start - The initiation of the successor activity depends upon the completion of the predecessor activity i.e., the successor activity cannot be started until the predecessor activity has already been completed.• Finish to finish - The completion of the successor activity depends upon the completion of the predecessor activity i.e., the successor activity cannot be completed until the predecessor activity has already been completed.• Start to start - The initiation of the successor activity depends upon the initiation of the predecessor activity i.e., the successor activity cannot be initiated until the predecessor activity has already been initiated.• Start to finish - The completion of the successor activity depends upon the initiation of the predecessor activity i.e., the successor activity cannot be completed until the predecessor activity has already been initiated.These types of dependencies describe the logical relationships between activities.Dependencies can be grouped into three categories:• Mandatory dependencies - These are the dependencies inherent to the schedule activities. For example, a software program must be developed before it can be tested. Mandatory dependencies are also referred to as hard logic.• Discretionary dependencies - These are the dependencies at the discretion of the project team. For example, the development for two parts of the system can happen in parallel and then integrated at a later point in time. It is not mandatory for the second module to wait until module one is over. Some of the guidelines for establishing discretionary dependencies can come from the knowledge of best practices within the given application area and from the previous experience of performing a similar project. Discretionary dependencies are also referred to as soft logic, preferential logic, or preferred logic.• External dependencies - An external dependency involves a relationship between a project activity and a non-project activity i.e., an activity outside the project. For example, lets say your application is migrating to a newer version of application server and it is supposed to be delivered & set up next week. You cant practically deploy and test your application until the server is delivered and set up. This is an example of an external dependency.The dependency between two schedule activities is an example of the logical relationships defined earlier in this chapter. Logical relationships can be displayed in schematic diagrams, called project schedule network diagrams, or just network diagrams. A common method to develop network diagrams is called the precedence diagramming method (PDM).


What is the difference between management and manager?

Management is an activity or function. Manager is the person who actually does the management


What is difference between manager and managment?

Management is an activity or function. Manager is the person who actually does the management


Problem relating to the implementation of activity based costing and activity based management system?

Answering "Problem relating to the implementation of activity based costing and activity based management system


What is the main difference between activity based costing and attribute based costing?

activity based costing does not promote TQM(total quality management) and continuous improvement but attribute based costing promotes the both.


What is the difference between activity and experiment?

the difference between activity and experiment is ...experiment is do


What is Robert Anthony Hierarchy of management activity?

Stategic , management and task


Why is management a primary component in entrepreneurial activity?

what is management primary component in entrepreneurial


What is the relationship between activity of management and activity of leadership?

One's a leader, one's a manger


Management's use of resources can best be evaluated by focusing on measures of?

Management's use of resources can best be evaluated by focusing on measures of activity. Activity, broadly defined, is something that is happening or being done.


Management is the same as administration how true is this?

management and administration is same they two are a group activity


What is cost slope in project management?

Cost slope is defined as the ratio of difference between Crash cost & Normal cost and difference between Normal Time & Crash Time. Crash Time is time taken by the activity when additional resources, overtime and other special measures are taken to speed up (crash) the activity.