answersLogoWhite

0

When setting out a cost budget you are using an estimated figure of what X will cost in the next Y months. This figure is not plucked out of the sky but calculated on prices at the time of budget creation plus addition % to cover the chances of inflation. When you reach the point of that expenditure it may be found that the cost will be

(1) As calculated

(2) Higher than calculated

(3) Lower than calculated

1,2, and 3 are the ACTUAL costs and can be compared against the Planned Cost data. Where the actual meets options 1 and 3 then the cost will normally be accepted. where the actual is option 2 then a review is undertaken to establish the need to allow the cost, reevaluated the need for the cost or to reject the expenditure outlay.

the actuals are recorded against the planned so that a historic pattern for the next planning term is used. It will also serve to inform the business plan of issues in future cost controls

User Avatar

Wiki User

12y ago

What else can I help you with?

Related Questions

What is the difference between actual costs and budgeted costs?

Actual Costs are costs which have occurred and can be reliably measured. Budgeted Costs are costs which have been estimated, possibly by using Forecasted Costs.


How can managers use accounting information to help control manufacturing overhead costs?

Managers compare the actual line item amounts for manufacturing overhead with the budgeted amounts. Managers investigate large differences between actual and budgeted amounts to identify the reasons why actual costs differ from planned or budgeted costs.


When is volume variance nonzero?

Volume variance is nonzero when there is a difference between the actual level of production achieved and the expected or budgeted level of production. This occurs when actual sales volume deviates from the planned sales volume, leading to changes in fixed costs allocated per unit. If the actual output is greater or less than what was anticipated, the fixed costs per unit will differ, resulting in a volume variance.


What is Production Variance?

In most production management systems, a "Planned" quantity and material cost is calculated based on the associated Bill of Materials (BOM) and Operatons being performed (Route) creating labor and overhead related costs. The "Actual" quantities, material costs, and labor/overhead costs are issued to a Work in Process (WIP) account and the quantities/values of the produced items are recieved from the WIP account. A variance usually occurs when there is a difference between the issued material cost plus labor and overhead and the recieved material cost of the produced item. The reasons for these variances can be differences in planned vs actual quantities, differences in system or planned cost of materials, labor, or overhead vs actual cost, or any other potential reason for an unplanned difference.


What is the difference between imputed costs and book costs?

Imputed costs do not appear in the historical cost accounting records for financial reporting. The actual cost incurred is recorder and is called a book cost.


What is the difference between over costing under costing?

Over costing means charging more costs to items than it's actual cost while under costing means charging less cost then actual costs.


What is the Difference between actual overhead costs and overhead costs applied?

The Actual overhead is calculated throughout the Production cycle for indirect cost associated to the production and the overhead costs applied is based on the fixed rate assigned against the machine or labour hours to be calculated for the difference b/w two are called under or over applied.


In accounting profit is the difference between what?

difference between revenue and costs


If the actual level of activity is 4 percent less than planned then the costs in the static budget should be reduced by 4 percent before comparing them to actual costs true or false?

FALSE according to my calculations it's false.


How do you calculate production volume variance?

Production volume variance is calculated by taking the difference between the actual production volume and the budgeted production volume, then multiplying that difference by the standard fixed overhead rate per unit. The formula is: [ \text{Production Volume Variance} = (\text{Actual Units Produced} - \text{Budgeted Units}) \times \text{Standard Fixed Overhead Rate per Unit} ] This variance helps to assess how well the actual production aligns with planned production levels and the impact on fixed overhead costs.


Importance of standard costing?

A valuable management tool, standard costing is part of cost accounting. Rather than using actual costs for direct material, labor and manufacturing overhead, standard costs are used to easily track variances and estimate profit.Though actual costs are still paid, standard costing is often used for inventories and cost of goods sold. The difference between standard and actual costs are known as variances. These variances are what make standard costing such a valuable practice for management. Management can quickly become aware of changes in budgeted costs by tracking the variances.When standard costing is used, you will often hear the terms unfavorable or favorable variance. This refers to changes in actual costs in relation to planned or standard costs. A favorable variance takes place when actual costs dip below standard costs. Conversely, if actual costs rise above standards, the variance is unfavorable.In regards to manufacturing companies, standard costs would first be seen as individual parts or pieces of the finished product. This means that the final standard cost will be the sum of the standard costs of each of the individual pieces of the product.


The positive difference between revenue and costs?

Profitability