Official tender with closed set of requirement and fixed price. Usually tender covers up to X% of “changes and additional requirements”, so small stuff can be changed and added later, but everything beyond that - nope.

You get an Excel or Word with several thousands of requirements (big and complex and trivial, with one line can cost zero and other can cost $1M to develop), you estimate the effort, add risk factors, and submit your proposal together with technical and managerial descriptions.

Good luck.

Anything that both satisfies their requirements as-written, and fits into technical description that was submitted will (must) be accepted by the customer - or they will have to bargain like “let’s cancel this requirement, but instead please implement that one”.

For governmental / military project managing all those requirements, what was amended, what was added, who owes what to whom, how it affects timelines, subcontractors (sometimes they are enforced by the customer and paid directly by him), is a full time and very non trivial job.

There are many types of projects that can’t be managed in Agile way, or delivered in Agile way (they still can be developed in Agile way, as it is internal matter of the dev team).

Customer won’t see anything before first review (that was requested as part of the tender, and was budgeted for).

Oh, forgot the reviews.

Interface Design Review, Integration Design Review, HMI Design Review, Safety Committee, Cyber Committee, Field Experiment Design Review, most of them come twice (preliminary and critical), for some you can add third - “Readiness Review”.

For big project that are delivered in phases you do the whole set two-tree times, for features of each phase (obviously first set takes the most effort).

Don’t forget logistics - spare parts program, operator training, technician training, certification programs, delivery of trainers and simulators.

Multiple pair-integration sessions, separate entity that manages integration and coordination of all systems (not only software. To be able to deploy in X hours your software must boot up, but hardware must be able to work for some time even before AC lowered temp in the shelter to the “long-running-threshold” value. Think about hundreds of interdependencies).

Everything must be coordinated.

Then come field tests. Test grounds must be booked, plans reviewed, safety issues validated, roads and air space closed, all the stuff shipped, engineers and technicians sent over (sometimes hundreds of them). To prepare all that takes months if not years. and usually you can’t “move” it in time. If something is not ready - or experiment will be delayed (very big issue), or this feature won’t be tested at all (bad), or experiment plan will be amended to allow testing of whatever can be tested (non ideal, but acceptable).

Then, when everything works and you deliver it - sometimes it is only IOC - initial operational concept. That means - pilot version. Customer will play with it for a year or two, and then order more - with changes, both in hardware and software, to cover for all deficiencies discovered in this “evaluation” period.

So trust me, there are many projects where “push-to-production” just doesn’t have a chance.

You can’t “eventually” get Air Traffic Control system (and I am talking about ground component only, not real avionics) if you start with something that can handle one plane that flies on the straight line, and continuously improve it.

You can’t deliver a “minimally valuable product” for nuclear station management system, and improve it with two-weeks sprints.

You can develop it in this way “internally”, you can give it to QA so they will test only very specific stuff (use-cases and scenarios) that is already implemented, but you never give anything to the customer until is passes FAT, SAT and full integration tests.

Version release process (you know, from check-in through Jenkins etc) can take months, and cost hundred thousands of $$$ (and I don’t include field tests, let’s assume everything can be done in QA/Integration laboratories).

Cost is not an exaggeration:

$1M is cost of employing 6–8 engineers for a year. So if version validation takes 2–3 months (different subcontractors, different countries, supervision from the customer and various certification authorities), and all over there are 10 people working on that (system engineers, programmers, part of managerial effort goes into that, QA people, integrators) you easily get into $K250–300 area for a main contractor. Add to it internal expenses of the customer (it cost them too to get a new version, redeploy, train, etc) and subcontractors, and you are in half-million area. This is for small “maintenance” release, not major delivery of significantly new functionality.

So yes, there are projects that are rather be done using Waterfall approach.

User Avatar

Thaw dar

Lvl 2
3y ago
This answer is:
User Avatar
More answers
User Avatar

Anonymous

Lvl 1
3y ago

[object Object]

This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What Provide three examples of software projects that would be amenable to the waterfall model. Be specific.?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Provide three example of software projects that would be amenable to the incremental model?

Provide three examples of software projects that would be amenable to the incremental model. Be specific.


Provide the 3 example of projects that would be amenable to the incremental model Be specific?

provide three examples of software projects that would be amenable to the incremental model Be specific?" The incremental process accommodates uncertainty better than most process models [1], allows the delivery of partial solutions in an orderly and planned manner [1], and most importantly, reflects what really happens when complex systems are built.


What are three examples of software projects that would be amendable to the incremental model?

provide three example of software projects that would be amenable to the incremental model. be specific Software applications that are relatively easy to prototype almost always involve human-machine interaction and/or heavy computer graphics. Other applications that are sometimes amenable to prototyping are certain classes of mathematical algorithms, subset of command driven systems and other applications where results can be easily examined without real-time interaction. Applications that are more difficult to prototype include control and process control functions, many classes of real-time applications and embedded software.


Which software industries are using waterfall model for software development?

All industries are using the waterfall model for software development.


Limitations of project management?

This is a tricky questions, as it depends on the mythology. Project Management has no limitations as its not a methodology, however, methodologies such as Agile and Waterfall, have limitations. Agile doesn't scale well and only has proved itself in software projects, while waterfall is not very flexible when it comes to software projects (as they require a lot of changes).


Provide three examples of software projects that would be amenable to the prototyping model?

Software applications that are relatively easy to prototype almost always involve human-machine interaction and/or heavy computer graphics. Other applications that are sometimes amenable to prototyping are certain classes of mathematical algorithms, subset of command driven systems and other applications where results can be easily examined without real-time interaction. Applications that are more difficult to prototype include control and process control functions, many classes of real-time applications and embedded software.


What is Waterfall Solutions?

Waterfall is one of the software development life cycle model. Waterfall model has five stages.


What are the traditional lifecycle models for software development?

The primary one is called "Waterfall" because it all goes one way, never back.


Discuss the advantages of waterfall model?

Advantage: - 1-You get the software according to your demand. 2-It is best for small projects. 3-It is very much sequential & systematic.


Waterfall model of the software life cycle?

It consists of different stages of software life cycle.


Which model is simplest model in Software Development?

Waterfall model


What is the Difference between RAD model and waterfall model?

The RAD model, also known as the Rapid Application Development, is a linear software for creating prototypes. The Waterfall model is a sequential software.