In Critical Path Analysis using precedence diagrams (showing activities linked by logical connections/constraints e.g. Activity A must happen before Activity B), then the Earliest Start (Earliest Event Time?) is the earliest time that that activity can start according to the logical constraints of the precedence diagram and the constraint types (Finish to Start, Start to Start, Finish to Finish or Start to Finish).