Say you ask me to replace your old door with a new one at an agreed price. I then later discover that your frame is rotten, so before i put in the door, i have to replace the frame and the cost for that is an extra because it wasn't part of the initial agreement. So we call it a variation order. If you say you will pay for it, then i will do it, but if you say you won't pay for it, i will just put your new door on the old frame as initially agreed.

User Avatar

Wiki User

16y ago

What else can I help you with?

Continue Learning about Engineering

What is the difference between variation order and extra work in construction?

A variation order is when there is a decrease or increase in quantities in your original scope of work. While an extra work is a new item of work introduced which shall be added into your original scope and will be binded in your contract.


What are the advantages of organization in a construction project?

With the guidance of engineers, the architect's vision of a new building, most often laid out on blueprints will succeed if the construction process is organized. If this plan is not carried out properly, then the results will cause construction delays as work completed may need to be undone, in order for the structure it come to completion. here is an example of an unorganized building project using basic engineering principles. All the electric wiring, switches and cables should be installed before the floors and walls are constructed. If this is not done, then the work must be taken apart in order for the electric components to be installed.


Difference between variation order and site instruction?

Variation Order is a Site Instruction which have effect on Time, Quality and Cost. But if we entitled it as Site Instruction only, usually it does not have effect on Time, Quality and Cost.


What is Variation order in construction project?

A "variation order" is most often when some extra work gets added to a project after the contract has been signed.For instance, I contract to paint your house, and we agree on a price. Then you ask me to paint the shed too.That's extra work and materials that weren't in the original agreement, so it will be added to the contract and the final cost.It could also be additional work needed for hidden problems that weren't apparent at the time of the contract.Like maybe I contracted to replace your windows and when I get the old window out, it turns out that the framework is rotted and has to be replaced. That work wasn't part of the original agreement and price, so I'll ask you to sign a variation order that states you're going to pay me for the additional work.


What is an example for inversion?

In JFK's inaugural address, he says "United there is little we cannot do in a host of cooperative ventures. Divided there is little we can do." This is an example of inversion, specifically the part where he says "United there is little we cannot do," versus "Divided there is little we can do." (The actual definition of inversion is: Inverted order of words in a sentence (variation of the subject-ver-object order). Source: The Language of Composition. Editors: Shea, Scanlon, Aufses

Related Questions

What is Variation order in construction?

A variation order is a 'change' which the Architect may be issued to make to the drawings, such as putting in a new window. The Architect will then inform the builders of the variation.


Who is involved in a variation order in construction?

A variation order in construction typically involves the client, the main contractor, and potentially subcontractors, architects, and project managers. It is important for all parties to communicate effectively and document any changes to the original contract to prevent disputes and ensure the project progresses smoothly.


What is the difference between variation order and extra work in construction?

A variation order is when there is a decrease or increase in quantities in your original scope of work. While an extra work is a new item of work introduced which shall be added into your original scope and will be binded in your contract.


Who can one contact about a building contract for a new home?

Construction Contracts, Construction Rocket Lawyer, and Home Advisor are all places where an individual can go in order to obtain a building contract for a new home.


Why you use water proofing materials in building construction?

In order to stop rising and lateral penatrative damp.


What is the significance of the nucleotide bases in relation to variation?

The order in which that are sequenced and variation in that order.


Who issues a variation order?

A variation order is typically issued by the client or main contractor to instruct changes to the original scope of work in a construction project. These changes can be due to design alterations, unforeseen site conditions, or client preferences, and they require formal approval and documentation to modify the contract terms.


What are the advantages of organization in a construction project?

With the guidance of engineers, the architect's vision of a new building, most often laid out on blueprints will succeed if the construction process is organized. If this plan is not carried out properly, then the results will cause construction delays as work completed may need to be undone, in order for the structure it come to completion. here is an example of an unorganized building project using basic engineering principles. All the electric wiring, switches and cables should be installed before the floors and walls are constructed. If this is not done, then the work must be taken apart in order for the electric components to be installed.


How might big construction project like building of canals and large building lead to law and government?

Because with so much going on you need to have order or things can get out off hand.


What topics does Building Construction Illustrated cover?

The book Building Construction Illustrated delivers detailed information on the basic principles of the mechanics in building technology. It provides information about materials and major projects that architects should be aware of in order to achieve success, and uses beautifully created drawings to better illustrate the concepts explored within the text.


What is variation order in electrical?

variation order is the extra work done outside your original contract. you should have a variation order form filled and the clients authorization. all the records of material and labour charge should be recorded so that the client can be billed. an example of variation order is say if your contract says you to change the light bulb but found out that there is a wrong cable used and needs to rewire with new cable then u need to inform client and need their authorization in order to rewire them.