answersLogoWhite

0

Copper / brass /some people opt for gavlanized

User Avatar

Wiki User

16y ago

What else can I help you with?

Continue Learning about Engineering

What are materials that do not allow water to pass through them easily called?

Materials that do not allow water to pass through them easily are called "water-resistant" or "waterproof" materials. These materials can include plastics, certain types of rubber, and treated fabrics. They are often used in applications where moisture protection is essential, such as in outdoor gear, construction, and packaging. The effectiveness of these materials can vary based on their composition and treatment.


Differences between afbc and cfbc boilers?

(fbc) boiler to heat the Water that is mixed with a refractory material. With warming water temperatures will produce refractory materials that will ignite the oil in the water. The granular refractory materials are mixed with water. Refractory materials are heated in water to take it. c) boiler column. The steam comes out vertically. A) horizontal boiler. The steam comes out horizontally.


Why do houses in places that get heavy rains have sloping roof?

A sloped roof allows water to flow go off the roof. Otherwise, the accumulation of rain water on a roof and its weight could exceed the ability of the roof to support it and might collapse the roof. The accumulation of water would also decrease the ability of the covering material to keep water out of the inside of the structure.


How shall you make the hydrostatic pressure test or the steps to follow?

procedures in testing hydrostatic pressure in fluid(water)


Vacuum dewatered flooring?

This specification defines the material, mixing, placing, curing, constructional and other performance requirements for VACUUM DEWATERING CONCRETE SYSTEM for foncrete floor slab. Any other special requirements shown or noted on the drawings and directed by the Engineer-in-Charge shall govern over the provision of this specification. Actual work shall be Carrie out in accordance with this specification and in consultation with specialised firm undertaking the job to suit specific requirement at site such as rise and fall of the floor slab, providing dowels for pedestals etc. In case of conflict between clauses mentioned in this specification and those in any Indian Standard, this specification shall grown. MATERIAL: All materials of construction like cement, aggregatre, sand, water etc. GRADE OF CONCRETE: Minimum grade of concrete used shall be M15 conforming to IS-456. Only Design Mix Concrete shall be used. For other details like proportioning, batching, mixing, placing, curing etc. WATER SCOPE: This specification defines the material, mixing, placing, curing, constructional and other performance requirements for VACUUM DEWATERING CONCRETE SYSTEM for foncrete floor slab. Any other special requirements shown or noted on the drawings and directed by the Engineer-in-Charge shall govern over the provision of this specification. Actual work shall be Carrie out in accordance with this specification and in consultation with specialised firm undertaking the job to suit specific requirement at site such as rise and fall of the floor slab, providing dowels for pedestals etc. In case of conflict between clauses mentioned in this specification and those in any Indian Standard, this specification shall grown. MATERIAL: All materials of construction like cement, aggregatre, sand, water etc. GRADE OF CONCRETE: Minimum grade of concrete used shall be M15 conforming to IS-456. Only Design Mix Concrete shall be used. For other details like proportioning,batching, mixing, placing, curing etc. WATER-CEMENT RATIO: Water-cement ratio upto 0.65 shall be allowed to obtain better slumb & workability. Actual ratio shall be decided with approval of the Engineer-in-charge. Only measured quantity of water shall be used in the mix. SPECIAL REQUIREMENT: All works covered by this specification shall be crried out by an experienced agency having sufficient expertise in vacuum dewatering concrete system. Only skilled and experienced operators shall be employed for the purpose. Prior approval of the agency shall be obtained from the Engineer-in-Charge before starting the work. All the equipment shall be of approved and proven types and suitable for the work involved. CONCRETE LAYING: Concrete laying pattern shall be decided in consultation with the Engineer-in-Charge and with his approval. The maximum width of a slab strip shall not generally exceed 4 metres and minimum number of construction joints shall be used. Alternate slab strips shall be sequentially laid. Any damage to the already finished top surface shall be avoided. At construction joints no overflow of mortal or slurry on the already hardened surface shall be allowed while concreting the intermediate slab strip. Such construction joints shall be marked with a thread in a straight line while the concrete is still green. Continuity of reinforcement shall be maintained while laying concrete in slab strips. Edges at expansion joints shall be protected and proper arrangement of shear-transfer shall be provided standards. CONCRETE COMPACTION: After placing concrete in position, it shall be vibrated thoroughly using poker/needle vibrators and thereafter leveled with surface vibrators to produce a homogeneous and smooth concrete surface. In order to achieve a smooth surface to the satisfaction of the Engineering-in-Charge, surface vibrators shall be very carefully used by skilled operators. Over vibration resulting in excess mortar near the surface shall be avoided. DE WATERING: Suction mats shall be spread over the leveled fresh concrete surface and shall be connected by suction hose to the vacuum pumps for De-watering of surplus water in the concrete. During De-watering it shall be ensured that no cement/cement slurry is pumped out. FLOATING & TROWELING: This shall be done after De-watering by using skim floater(power floater. After this, surface shall be troweled with minimum two passes of power trowel to achieve a wear resistant surface to the satisfaction of the Engineer-in-Charge. CURING: However, all care shall be taken to avoid any stain any permanent stain on the surface. Any stain or permanent marking on the top surface shall be removed by approved means. APPROACH WORKING PLATFORM & FORM WORK: The Contractor shall arrange all arrange all approaches, scaffolding, working platforms etc. for carrying out the entire operation safely and in a work-man-like manner. The working area shall be nearly maintained and all the facilities required by the Engineer-in-Charge for proper supervision of the work shall be provided. TESTING OF FINISHED FLOOR: Contractor shall arrange for core cutting and testing of finished concrete over and above other field tests. Cores shall be taken after 28 days of concreting and tested as per relevant IS Codes. Core test results shall be compared with the normal cube test results taken from the same concrete. The average compressive strength of cores shall be minimum 40% higher than that of normal cube (15cm x 15cm x 15xm) test results. Minimum three cores for each day's work in the initial stages and as decided later by the Engineer-in-Charge shall be taken. The floor shall be properly rectified after cutting the cores with concrete of same mix using the same cement as earlier used and finished smoothly to match with the existing surface. The cut surface of the floor-concrete shall be coated with proper epoxy-based bonding compound before laying concrete to avoid shrinkage cracks or, alternatively, a non-shrink compound shall be added with concrete. PAYMENT: This clause shall apply to Item Rate tender only. Payment shall be made on cubic meter(m3) basis of actually finished work or as calculated from the approved construction drawings, whichever is less. The reinforcement used shall be measured and paid separately on weight basis. If you need Vacuum De-watering concrete flooring job work you can contact us:

Related Questions

Why are some materials absorbing water?

Materials that are porous, that is, that have pores or open areas within the material where gases or liquids can enter, will absorb and hold water as well as other materials. A good example is a sponge, which absorbs water through pores or openings and holds it inside.


What is the relationship of dissolved materials inside and outside the cell in a isotonic hypertonic and hypotonic solutions?

In an isotonic solution, the concentration of dissolved materials inside and outside the cell is the same, resulting in no net movement of water. In a hypertonic solution, the concentration of dissolved materials outside the cell is higher than inside, causing water to leave the cell and leading to cell shrinkage. In a hypotonic solution, the concentration of dissolved materials outside the cell is lower than inside, causing water to enter the cell and potentially leading to cell swelling or bursting.


What material is inside the balloon?

Balloons are typically inflated with air, helium, or water. They are made of latex, rubber, or plastic materials.


Does the cell wall support and protect the cell?

Yes it does.It prevents materials from getting into your cells like DNA and water.


What are five that plants need to survive on land?

For plants to survive on land, they must have ways to obtain water and other materials from their surroundings, retain water, transport materials throughout the plant, support their bodies, and reproduce successfully. :D


What five adaptation that plants need to survive on land?

For plants to survive on land, they must have ways to obtain water and other materials from their surroundings, retain water, transport materials throughout the plant, support their bodies, and reproduce successfully. :D


Why some materials sinks in water while others do not?

Materials sink in water if their density is greater than the density of water. This means that their mass is more concentrated in a given volume compared to water. Objects that float have a density less than water, which allows them to displace enough water to support their weight and remain buoyant.


How can I effectively build a water filter at home using simple materials?

To build a water filter at home using simple materials, you can use a plastic bottle, sand, gravel, and activated charcoal. Cut the bottom of the bottle, layer the materials inside in this order: gravel, sand, charcoal. Pour water through the top and collect the filtered water at the bottom. This DIY filter can help remove impurities from water.


How can I make a water filter at home?

To make a water filter at home, you can use materials like a plastic bottle, sand, gravel, and activated charcoal. Cut the bottom of the bottle, layer the materials inside in the order of gravel, sand, and charcoal, and pour water through the top. The filter will help remove impurities from the water.


Who said that sir give you this water that you may not thirst?

The Samarian woman:Jesus told her, "...whosoever drinketh of the Water that I shall give him shall never thirst; but the Water that I shall give him shall be in him a well of Water springing up into Everlasting Life."The woman saith unto Him, Sir, give me this Water, that I thirst not, neither come hither to draw." (John 4:14-15)


What materials dissolve in ocean water and how are these materials removed?

== == materials get into water by animals waste


Will the people be able to float on water if the strength of earth's gravity is doubled and Why?

No, the increased gravity would make it harder for people to float on water. The extra force pulling them down would make it more difficult for them to displace enough water to stay afloat without some external support.