Schedule control has a two-pronged goal; to ensure that the project is progressing on time as planned and to monitor any changes to this progress. As a project manager, you should be out in front of the project, performing the following tasks on a regular basis:
• Determining the current status of the project schedule
• Influencing the factors that generate schedule changes
• Determining whether the project schedule has changed. For ex: if some activities are running late
• Managing changes as they occur
You detect a schedule change by comparing the execution time to the time in the schedule baseline, which is a major input item into the schedule control process. This is formally called Control Schedule.
Controlling the project scope includes influencing factors that create changes to the scope, as well as managing change requests and controlling their impact when the change actually occurs.
While controlling the scope, you focus on the following tasks:
• Watch out for scope creep - Determine whether it has happened and correct the situation. Scope creep refers to scope changes applied without processing them though the change control process.
• Process the scope change requests through the integrated change control process for approval.
• Manage the implementation of scope changes after approval, as well as their impact across the project.
Controlling cost means monitoring and controlling updates and changes to costs, budget, and the cost baseline of the project. Monitoring and controlling costs has two dimensions to it: expenditure of project funds and the work performed as a result of those expenditures. One major aspect of cost monitoring and controlling is to determine the relationship between the expenditures and the accomplishments. The cost performance depends on this relationship. The other main aspect is to control the changes to the approved cost performance baseline.
To be more specific, monitoring and controlling the project cost includes the following tasks:
• Influence the factors that can create changes to the approved cost baseline.
• Monitor the following:
o Work performed against the funds expended
o Variance of cost performance from the approved baseline • Prevent unapproved changes from creeping into cost reports and expenditures.
• Act to keep cost overruns within the planned acceptable limits.
• Ensure the following:
o Change requests are dealt with in a timely fashion and managed as they occur.
o Expenditures do not exceed the approved budget by period or by total amount. Any change to the budget must be approved before implementation. • Communicate with the appropriate stakeholders about the cost associated with the approved changes.
Cost is monitored and controlled by using the Control Cost process
The job of the Project Manager is to (among many, of course): - Manage the project - Manage stakeholders - Monitor the project's budget and schedule - Develop the project plan - Manage project conflicts
EVM is a technique to monitor/track projects. EVM has 2 important index statistics: CPI and SPI. CPI is the cost performance index, and if it's >= 1 it means that the project is OK with the budget, if it's < 1, it means that the project is over-budget. SPI is the schedule performance index, and if it's >=1 it means that the project is on schedule or ahead of schedule, if it < 1, it means that the project is behind schedule.
Project performance is measured by comparing the project execution to the performance measurement baseline, which is an approved integrated plan for scope, schedule, and cost for the project, as explained here:• Cost baseline - This is the planned budget for the project over a time period, used as a basis against which to measure, monitor, and control the cost performance of the project. The cost performance is measured by comparing the actual cost to the planned cost over a time period.• Schedule baseline - This is a specific version of the project schedule developed from the schedule network analysis and the schedule model data. This is the approved version of the schedule with a start date and an end date, and it is used as a basis against which the project schedule performance is measured.• Scope baseline - This is the approved project scope that includes the approved project scope statement, the WBS based on the approved project scope statement, and the corresponding WBS dictionary.
Implementing a change control system in project management is important because it helps to manage and track changes to the project scope, schedule, and budget. This system ensures that any changes are properly evaluated, approved, and documented, helping to prevent scope creep, budget overruns, and schedule delays. It also provides transparency and accountability, allowing stakeholders to understand the impact of changes and make informed decisions. Overall, a change control system helps to maintain project quality, control risks, and ensure successful project delivery.
The primary goal of project cost management is to estimate the cost and to complete the project within the approved budget. This is one of the important activities because our bosses wouldn't approve if we exceed our approved budgets and it might have severe repercussions. Not to mention, finishing a project within budget with money to spare will always help you during your own appraisal! Cost management includes the following components: 1. Estimate cost - Develop the cost of the resources needed to complete the project, which includes schedule activities and outsourced/procured work. 2. Determine budget - Aggregate the costs of individual activities to establish a cost baseline that includes timing. 3. Control cost - Monitor and control the cost variance in the project execution. i.e., the difference between the planned cost and actual cost during execution, as well as changes to the project budget.
The job of the Project Manager is to (among many, of course): - Manage the project - Manage stakeholders - Monitor the project's budget and schedule - Develop the project plan - Manage project conflicts
EVM is a technique to monitor/track projects. EVM has 2 important index statistics: CPI and SPI. CPI is the cost performance index, and if it's >= 1 it means that the project is OK with the budget, if it's < 1, it means that the project is over-budget. SPI is the schedule performance index, and if it's >=1 it means that the project is on schedule or ahead of schedule, if it < 1, it means that the project is behind schedule.
The project control base typically includes elements such as the project schedule, budget, resources, and scope. However, risk management is not typically considered as part of the project control base, although it is an important aspect of project management.
If SPI < 1, then the project is behind schedule, otherwise it's on or ahead of schedule. If CPI < 1, then the project is over budget, otherwise it's on budget, or under budget.
They enable project managers to compare earned value against the project's performance in terms of scope, budget, and schedule
Project performance is measured by comparing the project execution to the performance measurement baseline, which is an approved integrated plan for scope, schedule, and cost for the project, as explained here:• Cost baseline - This is the planned budget for the project over a time period, used as a basis against which to measure, monitor, and control the cost performance of the project. The cost performance is measured by comparing the actual cost to the planned cost over a time period.• Schedule baseline - This is a specific version of the project schedule developed from the schedule network analysis and the schedule model data. This is the approved version of the schedule with a start date and an end date, and it is used as a basis against which the project schedule performance is measured.• Scope baseline - This is the approved project scope that includes the approved project scope statement, the WBS based on the approved project scope statement, and the corresponding WBS dictionary.
Project performance is measured by comparing the project execution to the performance measurement baseline, which is an approved integrated plan for scope, schedule, and cost for the project, as explained here:• Cost baseline - This is the planned budget for the project over a time period, used as a basis against which to measure, monitor, and control the cost performance of the project. The cost performance is measured by comparing the actual cost to the planned cost over a time period.• Schedule baseline - This is a specific version of the project schedule developed from the schedule network analysis and the schedule model data. This is the approved version of the schedule with a start date and an end date, and it is used as a basis against which the project schedule performance is measured.• Scope baseline - This is the approved project scope that includes the approved project scope statement, the WBS based on the approved project scope statement, and the corresponding WBS dictionary.
Implementing a change control system in project management is important because it helps to manage and track changes to the project scope, schedule, and budget. This system ensures that any changes are properly evaluated, approved, and documented, helping to prevent scope creep, budget overruns, and schedule delays. It also provides transparency and accountability, allowing stakeholders to understand the impact of changes and make informed decisions. Overall, a change control system helps to maintain project quality, control risks, and ensure successful project delivery.
how to monitor and control expenses against budget/
The primary goal of project cost management is to estimate the cost and to complete the project within the approved budget. This is one of the important activities because our bosses wouldn't approve if we exceed our approved budgets and it might have severe repercussions. Not to mention, finishing a project within budget with money to spare will always help you during your own appraisal! Cost management includes the following components: 1. Estimate cost - Develop the cost of the resources needed to complete the project, which includes schedule activities and outsourced/procured work. 2. Determine budget - Aggregate the costs of individual activities to establish a cost baseline that includes timing. 3. Control cost - Monitor and control the cost variance in the project execution. i.e., the difference between the planned cost and actual cost during execution, as well as changes to the project budget.
Project cost control is comparing the actual project cost against planned project cost.
Project managers are responsible for planning, executing, and overseeing projects from start to finish. They facilitate communication and collaboration among team members, set project goals and timelines, allocate resources, and monitor progress to ensure successful completion within budget and schedule constraints. Additionally, project managers often act as a liaison between stakeholders, clients, and team members to ensure all parties are informed and aligned.