"Load Factor" is an indicator of how steady an electrical load is over time.

If your electric billing rate includes both an Energy (kWh) and Demand (kW) charge, your load factor can be calculated by the following formula:

L.F. (percent) = [(Total kWh)/(# Days in Bill Cycle x 24 hrs/day)]/[Peak kW Demand]

If your load factor is low, you should look for ways to even out your electrical usage (i.e., shift energy intensive processes to periods of otherwise low usage).

By increasing load factor, you will reduce the impact of monthly demand (kW) charges on your bill.

Another way of looking at load factor is:

LF = average demand / peak demand

for a given period of time.

Load factor is the total energy consumed in a period (kWh) over maximum power that can be delivered(kW) in to no of hours (h) in that period.

Load factor = Energy consumed (kWh)/ max power (kW) x No. of hours (h)

User Avatar

Wiki User

2015-07-17 17:29:33
This answer is:
User Avatar
Study guides

Physics

20 cards

What type of circuit in which all parts are connected in a single loop

What angle is between 90 and 180

What condition has symptoms that include ringing buzzing or roaring in the ears or head

What is the transfer of energy as electromagnetic waves called

➡️
See all cards
4.0
40 Reviews

Add your answer:

Earn +20 pts
Q: What is the meaning of load factor?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Continue Learning about Natural Sciences

How is plant load factor calculated in power plants?

Plant Load Factor is the ratio of the actual output of a power plant over a period of time and its output if it had operated a full capacity of that time period. Plant Load Factor = Gross Generation / (Installed Capacity * Number of Hours)


What does a Lagging power factor mean?

underdampedAnswerA lagging power factor describes a situation in which the load current is lagging the supply voltage. This describes an inductive load, such as a motor, etc.


How many VA in 1 kilowatt?

In a.c. circuits, the watt is used to measure the true power of a load, and is determined by multiplying the supply voltage by the load current by the power-factor of the load. The volt ampere is used to measure the apparent power of a load, and is determined by multiplying the supply voltage by the load current. So the relationship between the watt and the volt ampere depends on the power factor of the load. For example a 100 VA load with a power factor of 0.8 (leading or lagging) will have a true power of 80 W.


How do you decide KVAR rating of capacitor bank?

Generally the capacitor rating of a bank are decided on the load factor.ie higher the KVAR higher the capacity.KVAR is the reactive power in which load angle differs with the load variation.If we know load factor multiply it by the sine angle which gives us the capacity of the cpapcity of the load bank. Generally the capacitor rating of a bank are decided on the load factor.ie higher the KVAR higher the capacity.KVAR is the reactive power in which load angle differs with the load variation.If we know load factor multiply it by the sine angle which gives us the capacity of the cpapcity of the load bank. Generally the capacitor rating of a bank are decided on the load factor.ie higher the KVAR higher the capacity.KVAR is the reactive power in which load angle differs with the load variation.If we know load factor multiply it by the sine angle which gives us the capacity of the cpapcity of the load bank.


What are three factor that affect creep?

Temperature, Time, and load

Related questions

What is the meaning of 'plant load factor'?

Answering "What is the meaning of 'plant load factor'


What is the other name of plant factor in load forecasting?

Load Factor


What does a negative value for a reactive power means?

Meaning it's a capacitive load. Leading power factor


Why the power factor improves with the load?

Power factor doesn't necessarily 'improve with the load', but it is determined by the load.


What is limit load factor in aviation?

the maximum load factor without structural damage to the aircraft. Load factor = 1 / (cos (angle of turn))


What is load factor in electricity?

It is the ratio of average load and Connected load. or Ratio of average load and Peak load. It indicates the utilization of the Plant. Higher the load factor better the utilization.


How can calculate maximum demand load?

maximum demand load can be calculated as: # maximum demand=demand factor * Connected load or by # maximum demand = connected load * Diversity Factor Note: Demand factor and diversity factor are NOT same


Why power factor can not be unity?

Power factor can be unity. If the load is purely resistive, then the load current and supply voltage are in phase, and the load will have unity power factor.


How many load factor equal to 1amp?

Load factor and current are not directly related


What power plant has high load factor?

Diesel Engine has high load factor


What is loss load factor?

A load loss factor, LLF,not loss load factor,Êis a calculation used by electrical utility companies to measure energy loss.Ê Its the ratio of average load loss to peak load loss.


How load factor is used?

Ratio of Average load to Maximum demand for a given period (for a day, month or year) is termed as Load factor or Plant Load Factor (PLF). Load Factor = Avg. Load*24/Max Demand*24 ......... For a Day. This Load factor is very important in the sense of calculating the overall generation cost. It is always less than 1. Higher the LOAD FACTOR of a power station,lesser the overall per unit generation cost of the power station.