0.6 cubic feet in one 80 lb bag. with there being 27 cubic feet in one cubic yard: 0.02 cubic yards per bag, in other words, it would take 45 - 80lb bags to yeild 1 cubic yard of concrete
10
This cannot be answered without knowing the width and depth.
Each 60 pounds bag of ready mix concrete will make .45 cubic foot of concrete. There are 27 cubic feet in a cubic yard. You will need 60 bags of 60 pound premixed concrete to make 1 cubic yard.
According to the related link below; the required amount to cover 1 square yard with 4 inches of concrete is 6.6 60 pounds bags.
typically one pallet, i believe theres 42 80lb bags on a pallet.
about 60 60lb bags
You will get not 2.3 cu ft you will probably need at least 50 to 60 bags to make cubic yard..
0.6 cubic feet in one 80 lb bag. with there being 27 cubic feet in one cubic yard: 0.02 cubic yards per bag, in other words, it would take 45 - 80lb bags to yeild 1 cubic yard of concrete
27 bags of 30kg bags of concrete bargs
about 60 60lb bags
20
Every 80lb concrete bag should be mixed with 4 quarts or 3.7 liters of water. This mixture will allow you to place aproximately .60cu/ft of concrete. There are 27 cu/ft in a cu/yd. The number then becomes .0222 yards per 80lb bag. Therefore 45 bags of 80lb (4000 psi) concrete ready mix will be enough for 1 yard of concrete.
This all depends on the mix you want. I assume you mean cement when you mention the 80lb bag of concrete. I have pushed concrete in my day... Bag cement mix is the same as concrete. Don't be funny. How many 80 pound bags will make 1 yard of concrete? I want a definitive answer this time.
Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.
40 bags of 90 will give you 1 yard
41 bags. Actual 40.5