Schedule management plan - Includes information regarding the project's duration buffers

Cost management plan - Contains information about the budget for managing risks

Communications management plan - Contains details about who will provide information about risks and responses

Organizational process assets - Includes information from past projects such as lessons learned

Enterprise environmental factors - Provides the organization's attitudes towards risk and tolerance for risk

Project scope statement - Contains the project deliverable and objectives that are the basis for future project decisions

User Avatar

Wiki User

11y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: The plan risk management process has six inputs. Match these inputs to the information that they provide?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What are some of the inputs fo the develop project management plan process?

Change control procedures Project management information systems Time management plan Project charter


What is process approach in total quality management?

Process approach is a management strategy in which processes, interaction between the processes, and inputs and outputs are managed by the managers. For more information, please visit the Related Link.


What are the inputs to the close project or phase process?

-Organizational process assets -The project management plan -Accepted deliverables


What inputs are usedduring the Close Project or Phase process?

Org process assets Accepted deliverables The project management plan


What are the inputs of the define scope process?

Organizational process assets Scope management plan The project charter Requirements documentation


What inputs are used during the close project or phase process?

the project management plan accepted deliverables organizational process assets


What inputs do you need when you develop a project management plan?

Time management plan Project charter Change control procedures project management information systems


What holds processed information before it is output?

An electronic tool that allows information to be inputs process and output is called?


What inputs do you use during the define scope process?

The Project Charter, Req Documents, Scope management Plan, Organizatioanl Process assets


What are the inputs to the Plan scope management process?

Project management plan Project charter Infrastructure of the performing organization Lessons learned from past projects


What are the inputs the manager must collect when developing the plan?

-Historical Information -Infrastucture Information -The project charter -The schedule management plan


How Operations Management ensures that the value of outputs at the end of the transformation process will be greater than the sum of all values of inputs?

Identify the various elements of the operations management input, transformation, output process?