To determine how many bags of 80 lb concrete make a cubic yard, you need to know that one cubic yard is equivalent to 27 cubic feet. An 80 lb bag of concrete typically covers about 0.6 cubic feet. Therefore, to fill one cubic yard, you would need approximately 45 bags of 80 lb concrete (27 cubic feet ÷ 0.6 cubic feet per bag ≈ 45).

User Avatar

AnswerBot

1mo ago

What else can I help you with?

Related Questions

How many bags of concrete to make a yard of concrete?

about 60 60lb bags


How many bags of concrete make up a square yard?

27 bags of 30kg bags of concrete bargs


How many 60 pound bags of concrete mix makes one yard?

According to the related link below; the required amount to cover 1 square yard with 4 inches of concrete is 6.6 60 pounds bags.


How many bags to make a cubic yard of concrete?

about 60 60lb bags


How many 60 pound bags of concrete are there in a half yard of concrete?

20


How many bags of cement would be needed for a cubic yard of concrete?

Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.


How many bags of 90 lb concrete mix to make one cu yard?

40 bags of 90 will give you 1 yard


How many bags at 80 lbs will equal a cubic yard of concrete?

41 bags. Actual 40.5


How many 60lb bags of concrete make one yard?

According to the FAQ on the Sakrete web site, Sixty of their sixty pound bags of High Strength concrete mix will be required to make a cubic yard of concrete.


How many 60 bags of concrete make one yard of concrete?

According to the related link below; the required amount to cover 1 square yard with 4 inches of concrete is 6.6 60 pounds bags.


How many 80lb bags of concrete are in a yard?

There are approximately 27 cubic feet in a cubic yard, and an 80-pound bag of concrete typically yields about 0.6 cubic feet. Therefore, to fill one cubic yard, you would need about 45 bags of 80-pound concrete.


How many 80 pound bags of concrete mix makes one yard four inches thick?

To make one yard of concrete from 80# bags you will need about 40-45 bags. Each bag is about .67 or 2/3 cubic foot. you will need 27 cubic feet to make 1 cubic yard. Cheaper to have a redimix truck deliver, and a lot less work.