The number of bags of cement needed per ton of sand depends on the specific mix ratio being used for concrete. A common mix ratio is 1 part cement to 2 parts sand to 4 parts gravel, which translates to about 0.5 tons of cement for every ton of sand. Therefore, if using 94-pound bags of cement, approximately 10 bags would be needed per ton of sand. However, it's essential to adjust the ratio based on the desired strength and application of the concrete.
7 bags per 1000 on mortar mix and half a truckload of "mortar" sand aught to do it.
Mix AExterior/ Exposed to dampnessArea of plaster per bag mixAll Purpose Cement Plaster thickness Area of wall (m2)Bags per (m2)110 mm120.08333333315 mm80.12520 mm60.166666667Mix BInterior/ Dry.Area of plaster per bag mixAll Purpose Cement Plaster thickness Area of wall (m2)Bags per (m2)110 mm150.06666666715 mm100.120 mm7.50.133333333
for preparing cement mortar C.M.(1:6) number of cement bags required are nearly 5.14 bags.calculation: for preparing 1 cu.m wet C.M(1:6), dry material required is 25% extra.therefore dry material required is 1.25 cu.mhence cement required=1.25/(1+6)=0.178 cu.m(sand required=0.178*6=1.068 cu.m)density of cement=1440 kg/cu.m=>cement required in kg=0.178*1440=256.32cu.mwt. of cement in kg per bag=50kgtherefore no. of bags required is=26.32/50=5.14bags.thank u.
Cement comes in bags that weigh 94 lbs. The volume of the bag is approximately 1 cubic foot. If you want to mix concrete which is a mixture of a coarse aggregate (gravel) and a fine aggregate (sand) and something to bond the two aggregates together (cement) then firstly you need to know the strength concrete that you require. For 1 cubic yard of 3000psi (pounds per square inch) strength you will need about 6 bags cement 12 cubic feet of sand and 24 cubic feet of gravel. Rule of thumb is the ratio should be 1:2:4 (cement:sand:gravel)
The number of bags of cement required to cover a square meter depends on the thickness of the application and the type of mix used. Generally, for a standard concrete mix, approximately 1 bag (usually 50 kg) can cover about 0.1 to 0.15 cubic meters. Therefore, for a thickness of about 10 cm, you might need around 3 to 5 bags of cement per square meter. It's best to consult specific mix design guidelines for precise calculations.
7 bags per 1000 on mortar mix and half a truckload of "mortar" sand aught to do it.
If a 20kg bag of cement=0.1m3 with 100 lots o 0.01 to 1m3 then you will need 12.5 bags per m3. So you need approx 11.5m3 of sand and 144 bags of cement (144 x 0.01 = 1.44m3) to give you a total of 12.94m3
11 bags
7 cement bags per 1 cubic meter of concrete......
it is 100 bags of sand/ballast
26 bags (40kgs cement bag)
On average, one bag of cement is needed per fence post.
35kg
Well, darling, if you want a concrete slab that's 5 inches thick, you'll need about 0.012 cubic meters of cement and 0.06 cubic meters of sand per square meter. Just make sure you mix it well and pour it like a boss. Good luck with your project, sugar!
8.4 beg (per beg 50Kg.) (420kg cement)
One cubic meter of concrete is equal to 1.308 cubic yards of concrete. If there are 5 1/2 bags of cement in 1 cubic yard of concrete, there would be 7.2 bags in 1 cubic meter of concrete. These are the 94 pound bags of portland cement or roughly 40kg bags so figure 8 bags total. Some will be left over
108