Usually for a design mix as per Indian Standards when the mix proportions are arrived for M25,the total cement consumption will be around 400 kg.From that the number of cement bags will be 8 numbers for 1 cum
M20 - 6.20bags
Yes. OPC 43 grade cement can be used to make M20 grade concrete.It can be used to make concrete up to M30 Grade.See related link.
260 kg/cu m
In an M20 concrete mix, which has a ratio of 1:1.5:3 (cement: sand: aggregates), approximately 7 to 8 bags of cement are needed for one cubic meter of concrete. This translates to about 350 to 400 kg of cement, considering a standard 50 kg bag. The exact number may vary based on factors like waste, mix adjustments, and specific project requirements.
how much tensile strength of M20 grade concrete at 28 Days
concrete and cement
M20 - 6.20bags
80cft
Yes. OPC 43 grade cement can be used to make M20 grade concrete.It can be used to make concrete up to M30 Grade.See related link.
260 kg/cu m
1:1.5:3:0.45 (cement,fine aggregate,coarse aggregate, water cement ratio)
density of send and aggrigate
In an M20 concrete mix, which has a ratio of 1:1.5:3 (cement: sand: aggregates), approximately 7 to 8 bags of cement are needed for one cubic meter of concrete. This translates to about 350 to 400 kg of cement, considering a standard 50 kg bag. The exact number may vary based on factors like waste, mix adjustments, and specific project requirements.
M20 grade - 1:1.5:3Cement required - 360 kgs per m3Cement required - 7.2 bags.
For M10 (1:3:6) Grade of concrete cement bag consumed = 4.4 bags/cum M15(1:2:4) Grade of concrete cement bag consumed = 6.6 bag/cum M20(1:1.5:3) Grade of concrete cement bag consumed = 8.2 bag/cum
how much tensile strength of M20 grade concrete at 28 Days
Cement : Fine Aggregate : Coarse Aggregate 1 : 1.5 : 3