That is approximately 5,300 pounds.
M20 - 6.20bags
In M20 grade concrete, the mix ratio is typically 1:1.5:3 (cement: sand: aggregates). For one cubic meter of concrete, you generally need about 7 to 8 bags of cement, as one bag of cement is approximately 50 kg. This equates to roughly 350 kg of cement per cubic meter, which aligns with the M20 mix design requirements.
how much tensile strength of M20 grade concrete at 28 Days
In an M20 concrete mix, which has a ratio of 1:1.5:3 (cement: sand: aggregates), approximately 7 to 8 bags of cement are needed for one cubic meter of concrete. This translates to about 350 to 400 kg of cement, considering a standard 50 kg bag. The exact number may vary based on factors like waste, mix adjustments, and specific project requirements.
my big hole
o
M20 - 6.20bags
In M20 grade concrete, the mix ratio is typically 1:1.5:3 (cement: sand: aggregates). For one cubic meter of concrete, you generally need about 7 to 8 bags of cement, as one bag of cement is approximately 50 kg. This equates to roughly 350 kg of cement per cubic meter, which aligns with the M20 mix design requirements.
315 Kg/M3 approx.
For a 1000 sqft slab with a thickness of 4 inches, you would need approximately 33 cubic meters of concrete. This calculation is based on the assumption that 1 cubic yard of concrete covers 81 square feet at 4 inches thick.
M20 grade - 1:1.5:3Cement required - 360 kgs per m3Cement required - 7.2 bags.
It depends on the Grade of Concrete. general grades are M15, M20, M25 etc. here are the nos. of bag required -------------------Bag for 1 cum---------------Bag for 5 cum M15------------------- 6.4----------------------------32 M20-------------------- 8-----------------------------40 M25--------------------12----------------------------60
how much tensile strength of M20 grade concrete at 28 Days
concrete and cement
In an M20 concrete mix, which has a ratio of 1:1.5:3 (cement: sand: aggregates), approximately 7 to 8 bags of cement are needed for one cubic meter of concrete. This translates to about 350 to 400 kg of cement, considering a standard 50 kg bag. The exact number may vary based on factors like waste, mix adjustments, and specific project requirements.
For M10 (1:3:6) Grade of concrete cement bag consumed = 4.4 bags/cum M15(1:2:4) Grade of concrete cement bag consumed = 6.6 bag/cum M20(1:1.5:3) Grade of concrete cement bag consumed = 8.2 bag/cum
80cft