Continue Learning about Management

What is acquisition decision memorandum?

"A memorandum signed by the Milestone Decision Authority (MDA) that documents decisions made as the result of a Milestone Decision Review (MDR) or decision review." -ACQuipedia


What is the difference between a milestone and a KPI?

It depends. In a project, a milestone refers to a significant or important event (marker) of decision points in a system or product development cycle. On the other hand, a key performance indicator (KPI) is a set of quantifiable measures to gauge the performance of a system.


Is the capability development document prepared to support a milestone c decision and doucments the user's operaitonal performance capabilities in the terms of thresholds and objectives?

No. It is the capability PRODUCTION document. ref: DAU Course ACQ101 lesson 1.3


How can I add milestones in MS Project?

To add milestones in MS Project, go to the Gantt Chart view, select the task where you want to add a milestone, right-click on the task, and choose "Add Milestone." You can also change an existing task to a milestone by checking the "Mark Task as Milestone" box in the Task Information window. Milestones are important points in your project that signify a significant event or achievement.


How can I effectively write a milestone in a project plan?

To effectively write a milestone in a project plan, clearly define a significant achievement or event that marks progress towards project goals. Include a specific description, target date, and criteria for completion. Ensure the milestone is measurable, realistic, and aligns with project objectives.

Related Questions

The Acquisition Strategy should normally be generated using an integrated product team (IPT) approach including representation from all of the players listed below EXCEPT the .?

Milestone decision authority


What is acquisition decision memorandum?

"A memorandum signed by the Milestone Decision Authority (MDA) that documents decisions made as the result of a Milestone Decision Review (MDR) or decision review." -ACQuipedia


An Acquisition Program Baseline (APB) is used to document the cost schedule and performance thresholds and objectives of a program beginning at program initiation. The APB is a formal agreement signed?

Program Manger/ Milestone decision authority


As the Program Manager of an acquisition program prior to which milestone will you ensure that the appropriate logistics considerations and test points are described in the Test and Evaluation Master?

milestone c


The following is an example of information that can be considered by the Milestone Decision Authority (MDA) at Milestone B?

Validates first and approved CCD


What authorizes entry into the Engineering and Manufacturing Development (EMD) phase?

Entry into the Engineering and Manufacturing Development (EMD) phase is authorized by Milestone B, where the program receives approval to proceed from the Milestone Decision Authority (MDA) based on the program's successful completion of the technology development phase and achievement of key performance parameters.


For a standard acquisition program the User produces the finalizing the operational requirements for the production system in support of Milestone C?

CPD


What is the purpose of the Milestone C decision?

Approval at Milestone C is dependent on an approved CPD, compliance with the DoD strategic plan and demonstration that the system is affordable throughout the life cycle. The MDA also approves the updated acquisiton strategy and the acquisition decision memorandum at Milestone C.


Who makes the financial recommendation to the component acquisition executive for each milestone for acat ii programs?

Service or Component Assistant Secretary for Financial Management.


Is the Milestone Decision Authority is responsible for establishing the Critical Operational Issues (COIs) that will be addressed in testing?

False


Program Manager should notify the Milestone Decision Authority within 90 days of the occurrence?

false


For programs ACAT II and below who makes the financial recommendation to the Component Acquisition Executive for each milestone?

Service or Component Assistant Secretary for Financial Management