The work done on the crate is calculated using the equation Work = Force x Distance. Given the time (4 s) and distance (2 m), we would need additional information such as the force applied to the crate to determine the total work done.
The work done on the crate would be 40 joules (work = force x distance).
No, the work done on the crate by the rope is not zero. The work done is equal to the force exerted by the rope multiplied by the distance the crate is pulled. The fact that the crate pulls back on the rope in accordance with Newton's Third Law does not cancel out the work done by the rope.
We have no way of knowing what power the machine was rated for, but with the information given in the question, we can calculate the power it delivered during the crate-lift: It was (1.96) x (mass of the crate in kilograms) x (distance the crate was lifted in meters) watts.
The work done in lifting the crate is equal to its change in potential energy: ( \text{Work} = \text{Force} \times \text{distance} = m \cdot g \cdot h ). The power required is the work done divided by the time taken: ( \text{Power} = \frac{\text{Work}}{\text{time}} ). Plug in the values to calculate the power required.
The work done by a crane lifting a 240 kg crate to a height of 165 meters is equal to the change in potential energy of the crate. The work done can be calculated using the formula: Work = force x distance. In this case, the force is equal to the weight of the crate (240 kg x 9.8 m/s^2) and the distance is 165 meters.
The work done on the crate would be 40 joules (work = force x distance).
w=2.9kilojoules..
No, the work done on the crate by the rope is not zero. The work done is equal to the force exerted by the rope multiplied by the distance the crate is pulled. The fact that the crate pulls back on the rope in accordance with Newton's Third Law does not cancel out the work done by the rope.
We have no way of knowing what power the machine was rated for, but with the information given in the question, we can calculate the power it delivered during the crate-lift: It was (1.96) x (mass of the crate in kilograms) x (distance the crate was lifted in meters) watts.
The work done in lifting the crate is equal to its change in potential energy: ( \text{Work} = \text{Force} \times \text{distance} = m \cdot g \cdot h ). The power required is the work done divided by the time taken: ( \text{Power} = \frac{\text{Work}}{\text{time}} ). Plug in the values to calculate the power required.
The work done by a crane lifting a 240 kg crate to a height of 165 meters is equal to the change in potential energy of the crate. The work done can be calculated using the formula: Work = force x distance. In this case, the force is equal to the weight of the crate (240 kg x 9.8 m/s^2) and the distance is 165 meters.
The work done on the crate would be 4000 joules (W = F x d), as work is the product of force (200 N) and distance (20 m).
The work done when pushing a crate with a force N across a distance M on a floor depends on the angle between the force and the direction of motion. If the force is applied in the same direction as motion, work done is N * M. If the force is applied at an angle, work done is N * M * cos(theta), where theta is the angle between the force and direction of motion.
80 J
The work done by the movers can be calculated using the work-energy principle. The work done can be found by multiplying the force of friction by the distance the crate was moved. The force of friction is the product of the coefficient of friction and the normal force (weight of the crate). The work done will be equal to the force of friction multiplied by the distance moved.
The work done to lift the crate is equal to the gravitational potential energy gained: Work = force x distance = weight x height. Here, Work = 50kg x 9.8m/s^2 x 10m = 4900 Joules. Power is work done per unit time, so Power = Work / time = 4900J / 5s = 980 Watts. Therefore, the power rating of the machine is 980 Watts.
Work = force x distance = Newtons x meters = 1937 Joules.