What is contained in a project baseline?

Updated: 8/18/2019
User Avatar

Wiki User

11y ago

Best Answer

Project baselines include, but are not limited to:

  • Schedule baseline- Fixed project schedule used in measuring project progress and contract performance. Any change caused by change in scope of the project invalidates the original schedule and necessitates a new baseline schedule.
  • Cost baseline- is the basis for the earned value reporting system. It is the budget for the estimated cost of the project spread over the time periods of the project.
  • Scope baseline- includes the project scope statement, the work breakdown structure (WBS) and WBS dictionary. If there are work packages that do not get performed or if they do not fulfill the requirements set out for them, then the scope baseline is not met. The performance of the PM as well as the rest of the team is derived from how well the project conforms to this baseline.
  • Quality baseline-The basis for which project quality is measured and reported
User Avatar

Wiki User

11y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is contained in a project baseline?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What is baseline project plan?

A Baseline Project Plan is the Project Management Plan that is created by the Project Manager and is approved by the Project Sponsor and the Senior Management. The Approved/baseline plan outlines how the project will be handled from start to finish and is like the bible for the project


What is a baseline plan?

A Baseline Project Plan is the Project Management Plan that is created by the Project Manager and is approved by the Project Sponsor and the Senior Management. The Approved/baseline plan outlines how the project will be handled from start to finish and is like the bible for the project


After project initation the project baseline must be?

documented,communicated,and updated


After project initiation the project baseline mst be?

docmented,communicated,updated


What are the main steps to tackle in creating a project plan?

There can be many steps in creating a project plan. First, explain the project. Then, define, hold a meeting, develop a statement, develop a baseline, and create baseline plans.


How is the baseline reviewed?

The baseline is reviewed by the customer. It's just a way of making sure that the contractor is using the agreed on contract when implementing the project.


What are the primary configuration baselines?

Functional Baseline: initial specifications established; contract, etc.Allocated Baseline: state of work products once requirements are approvedDevelopmental Baseline: state of work products amid developmentProduct Baseline: contains the releasable contents of the project


How does a baseline budget facilitate integrating the planning and controlling of projects?

Baseline budgeting facilitates integrating the planning and controlling of projects by providing the baseline budget itself. Having a baseline budget?æplan with time phases allows better project planning.


What is an estimated cost of a project called?

It is called the Cost Budget or the Budget Baseline


The baseline for the project is established in which phase?

Type your answer here... during the proposal effort


What are area of improvements of an IT project manager?

Opinions may vary. Some IT project managers rate themselves in every project and uses this as their baseline for improvements.


What information from the subsidiary plans is included in the project management?

Performance targets Schedule baseline