Wet concrete is approximately 150 pounds per cubic foot. So 80 pounds is approximately 1/50 th of a cubic yard.
This cannot be answered without knowing the width and depth.
A typical 80-pound bag of concrete mix yields about 0.6 cubic feet of concrete. A 3-yard mixer has a capacity of 81 cubic feet (3 cubic yards). To fill the mixer, you would need approximately 135 bags of 80-pound concrete mix, since 81 cubic feet divided by 0.6 cubic feet per bag equals about 135 bags.
0.6 cu yds 0.6 yards is incorrect. According to quikrete's website it would require 46 80# bags of concrete to cover 81 square feet at 4" thick, which is one cubic yard. Dividing 46 by 1 yard gives us approximately 0.022 yards per bag.
To determine how many sacks of ready mix are needed for one cubic yard, it typically depends on the size of the sacks. For example, a standard 80-pound bag of ready mix concrete yields about 0.6 cubic feet. Therefore, you would need approximately 45 bags (80-pound sacks) to make one cubic yard, as one cubic yard equals 27 cubic feet. If using different bag weights, the number of sacks required will vary accordingly.
0.6 cubic feet in one 80 lb bag. with there being 27 cubic feet in one cubic yard: 0.02 cubic yards per bag, in other words, it would take 45 - 80lb bags to yeild 1 cubic yard of concrete
41 bags. Actual 40.5
80
Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.
it takes 45 Bags of 80# mix to make a cubic yard
This cannot be answered without knowing the width and depth.
there are 27 cubic feet in one cubic yard.
This all depends on the mix you want. I assume you mean cement when you mention the 80lb bag of concrete. I have pushed concrete in my day... Bag cement mix is the same as concrete. Don't be funny. How many 80 pound bags will make 1 yard of concrete? I want a definitive answer this time.
4 inches = 1/3 foot27 cubic feet = 1 cubic yardVolume = 80 x 1/3 = 80/3 cubic feet = 80/81cubic yard = about 0.987654321 (really!)
There is 0.45 cubic feet in a 60-lb bag, so you need 60 bags. If you go to 80-lb bags, there's 0.60 cubic feet and you need 45 bags.
A typical 80-pound bag of concrete mix yields about 0.6 cubic feet of concrete. A 3-yard mixer has a capacity of 81 cubic feet (3 cubic yards). To fill the mixer, you would need approximately 135 bags of 80-pound concrete mix, since 81 cubic feet divided by 0.6 cubic feet per bag equals about 135 bags.
To make one yard of concrete from 80# bags you will need about 40-45 bags. Each bag is about .67 or 2/3 cubic foot. you will need 27 cubic feet to make 1 cubic yard. Cheaper to have a redimix truck deliver, and a lot less work.
0.6 cu yds 0.6 yards is incorrect. According to quikrete's website it would require 46 80# bags of concrete to cover 81 square feet at 4" thick, which is one cubic yard. Dividing 46 by 1 yard gives us approximately 0.022 yards per bag.