M20 - 6.20bags
One cubic metre of concrete weighs 2.5 Tonnes. Typically, 1m3 of concrete is made up of 350Kg of cement, 700Kg of sand, 1,200Kg of chippings and 150 Litres of water.
For M20 grade concrete mix proportion=1:1.5:3 And dry volume factor is 54 percent. Hence, we required to find quantities for 1.54 cum concrete. cement required=(1/5.5) x (1.54)=0.27 cum, Sand required=(1.5/5.5) x (1.54)=4.2 cum, Stone chips required=(3/5.5) x (1.54)=0.84 cum.
Type your answer here... 11.2
In grade 25 concrete, which typically has a mix ratio of 1:1:2 (cement:sand:aggregate), approximately 0.5 cubic metres of sand is required per cubic metre of concrete. Since the density of sand is about 1,600 kg per cubic metre, this translates to around 800 kg of sand needed for one cubic metre of grade 25 concrete. This amount can vary slightly based on the specific mix design and moisture content of the sand.
M20 - 6.20bags
M 15 grade proportion - 1:2:4 (cement:FA:CA)Cement required in kgs - 325 kg per cu.mNo. of bags required - 6.50
For M25 grade concrete, the mix proportion is typically 1:1:2 (cement:sand:aggregate). This means for 1 cubic meter of concrete, you would need 1/4 cubic meter of cement. As 1 cubic meter is equivalent to 35.32 cubic feet, and one bag of cement usually covers around 0.035 cubic meters, you would need approximately 7-8 bags of cement for 1 cubic meter of M25 grade concrete.
To determine how many 50 kg cement bags are required for 1 cubic meter of Grade 30 concrete, we need to break down the mix ratio and calculate the cement content based on that. Grade 30 Concrete Mix Ratio Grade 30 concrete typically has a mix ratio of 1:2:3 (Cement: Sand: Aggregate) by volume. This means: 1 part cement 2 parts sand 3 parts aggregate (gravel) However, the actual proportion of cement required can vary slightly depending on the specific mix design used by a contractor or engineer. For standard Grade 30 concrete, the cement content is typically around 350 to 400 kg per cubic meter. Since each cement bag weighs 50 kg, the number of bags required for 1 cubic meter of Grade 30 concrete would be: Number of bags = 350 kg / 50 kg = 7 bags
15 milligrams
For M10 (1:3:6) Grade of concrete cement bag consumed = 4.4 bags/cum M15(1:2:4) Grade of concrete cement bag consumed = 6.6 bag/cum M20(1:1.5:3) Grade of concrete cement bag consumed = 8.2 bag/cum
315 Kg/M3 approx.
One cubic metre of concrete weighs 2.5 Tonnes. Typically, 1m3 of concrete is made up of 350Kg of cement, 700Kg of sand, 1,200Kg of chippings and 150 Litres of water.
M20 grade - 1:1.5:3Cement required - 360 kgs per m3Cement required - 7.2 bags.
M 15 grade - 1:2:4Cement bags required - 6.5 bagsCement required - 325 kgs
For M20 grade concrete mix proportion=1:1.5:3 And dry volume factor is 54 percent. Hence, we required to find quantities for 1.54 cum concrete. cement required=(1/5.5) x (1.54)=0.27 cum, Sand required=(1.5/5.5) x (1.54)=4.2 cum, Stone chips required=(3/5.5) x (1.54)=0.84 cum.
Type your answer here... 11.2